Generation company of joint stock company (Infopro: Planning of the modes)

Customers: Generation company of joint stock company

Kazan; Power

Contractors: InfoPro Group
Product: InfoPro: Planning of the modes

Project date: 2012/07

Implementation of information complex by calculation and forecasting of TEI on Generation company branch of JSC the Zainsk state district power plant

Status: Completed project

Implementation term: 12 months

Problem: need of information complex by calculation and forecasting of TEI on Generation company branch of JSC the Zainsk state district power plant is caused by the following reasons:

  • Lack of the modern software for calculation of the TEI meeting the requirements:

o Ensuring integrity of data; o Flexibility in setup of calculations; o Possibility of formation of unlimited number of report forms; o Integration with primary data sources; o Integration into the MS Office software package;

  • Lack of the software for forecasting of TEI.

Solution: as the basic software product for project implementation the information system of calculation TEI of the ASTEP stations is selected.

Results:

  • Reduction of time expenditure on calculation of TEI allows to carry out daily calculations and calculations for watches in full of model 15506-1, forms No. of 3-that (power) and normative model;
  • An opportunity to qualitatively predict specific fuel consumption in volume of the normative model according to the recommendations of the Ministry of Industry and Energy and the FST is had;
  • Reporting process is automated.