Algo Pizza completed installation of the engineering systems of the enterprise

Customers: Algo Pizza

Krasnogorsk; Food industry

Contractors: LanKey
Product: Complex projects of creation of the engineering systems

Project date: 2013/07  - 2013/09

Content

On September 24, 2013 the LanKey company announced installation of the climatic and electric systems in Algo Pizza cafe in the city of Krasnogorsk.

Project Objectives

Due to the reconstruction of one of Algo Pizz's pizzerias there was a need for installation of the engineering systems for cafe premises. A project objective - ensuring necessary air exchange and comfortable parameters of air temperature according to the work documentation. In addition to installation of a climatic system there was a task - to upgrade a power supply system.

Project Progress

The LanKey system integrator picked up the equipment, executed installation of a forced-air and exhaust system with a water heater. Five internal blocks of cassette type and one internal block of wall type are installed.

Along with works on installation of the ventilation and air conditioning system specialists of LanKey carried out works on upgrade of a power supply system which included laying of the distribution cable to the existing input distribution frame, installation of boards for a household, lighting power supply and air conditioning systems, laying of group lines from boards to jobs, lamps and conditioners. After implementation of installation of an electrical cable system, it was tested by the certified cable electrolaboratory with providing test reports to the customer.

Project Results

Result of the performed works:

  • modern climatic system
  • safe failsafe power supply system.