Customers: Krasnoyarsk hydroelectric power station Contractors: LANIT Siberia (before LANIT Krasnoyarsk) Product: SCS projects and wireless network infrastructureProject date: 2013/08 - 2013/12
|
On December 16, 2013 the LANIT Krasnoyarsk company announced completion of expansion and reconstruction of the systems of fiber optic network JSC Krasnoyarsk Hydroelectric Power Station.
Project Progress
Within the project specialists of LANIT Krasnoyarsk supplied the equipment, parts, spare parts and accessories - according to the project documentation, constructed the systems of the communication fiber lines (CFL), carried out acceptance tests and prepared executive documentation.
Project Results
A system is constructed and started in time. More than 20 km of the optical cable on different marks of a dam are mounted (from-30 m to +100 m from Yenisei River level). 51 telecommunication cabinets are mounted, 1600 weldings of optical fiber are made.
Sergey Kaminsky, the CEO of JSC Krasnoyarsk Hydroelectric Power Station, noted: "All works are performed in full accordance with the diagram, and at times even advancing it. As a result, at us is qualitatively constructed by the fiber-optic communication line and a detailed set of the executive project documentation. We are happy with cooperation with LANIT Krasnoyarsk as we achieved all project objectives".
"Features of project implementation on the Krasnoyarsk hydroelectric power station was the fact that we worked at the operating sensitive site. Besides, the customer made changes directly on the course of creation of a system. Thanks to coordination of our collective and high professionalism of all project participants it was succeeded to solve successfully all assigned tasks with required quality and in time", - Pyotr Kondratyev, the director of the company of LANIT Krasnoyarsk emphasized.