Project

"The center of technologies of virtualization" completed installation of a system of regular power supply

Customers: Center of technologies of virtualization

Novosibirsk; Information technologies

Contractors: Stins Coman
Product: Complex projects of creation of the engineering systems

Project date: 2013/12  - 2014/02

On February 13, 2014 it became known of project completion on installation of no break power supply system of the DPC power center for "The center of technologies of virtualization". The project was performed by "Stins Coman" (SC) company.

Project Progress

In the course of execution of the project commissioning and installation four the 1680 kVA the diesel-rotor uninterruptible power supply units (DRUPSU) Hitec Power Protection everyone are carried out. This power supply system at an overall load on the diesel ensures smooth operation of a data processing center within eight hours.

In addition specialists of SKIR redesigned and mounted in the power center building power and information cable passages, the cooling system (with leak check, a possibility of work with different coolants), the fuel system and the system of a gas-exhaust.