"DTEK Kurakhovskaya of TPP" completed installation of climatic installation

Customers: DTEK Kurakhovskaya of TPP

Donetsk; Power

Contractors: AMI
Product: Complex projects of creation of the engineering systems

Project date: 2014/01  - 2014/03

On March 24, 2014 the AMI company announced completion of creation of a system of maintenance of climate in DTEK Kurakhovskaya of TPP.

Project Progress

The conditioning system in the block control panel (BCP) of power units of TPP is created using the columned Mitsubishi Electric conditioners equipped with the block for all-weather providing necessary temperature condition indoors at outside air temperatures from -30 ° up to +45 °. Total refrigerating capacity of a system is 28 kW.

The forced-air and exhaust Lessar ventilation unit with recuperation of heat provides cleaning, heating, supply of fresh air, removal of an exhaust air from the premises of dispatching office of the turbine hall.

Project Results

Within the project implementation of conditioning systems and ventilation in a block control panel of power units DTEK of Kurakhovsky thermal power plant is executed.

"The main complexity during creation of a system of maintenance of climate - need of laying of trunks at the height more than 40 meters over the premises of BShchU of power units. All works are carried out in the conditions of the working production, at the same time a part of works was made in proximity from pipelines with a superheated steam of high pressure that required extra care and professionalism", - Valentin Mironov, the chief engineer of AMI company noted.