CROC implemented DPC in Inteza Bank

Customers: Inteza bank (KMB-Bank is Bank of financing of small business)

Contractors: Croc
Product: DPC of CROC Compressor

Project date: 2014/10

Within the project the local computer network was unrolled, the storage area network is implemented, are installed a backup system and data recovery. DWH of EMC, the NR tape libraries, Cisco switches and Brocade were used.

"Placement of reserve DPC on the third-party platform gave us an opportunity to quickly increase computing resources" — the director of the department of information technologies of Inteza Bank Boris Golovatskikh said.
"the RDPC is a product of "manual assembly". In data center Compressor we designed a reliable complex taking into account individual requirements of the customer for fault tolerance, delivered and mounted the necessary systems, synchronized RDPC with other data centers of Bank, including, in Italy. Creation of all necessary computing and network infrastructure took 8 months" — Pavel Kolmychek, the head of network of data centers of CROC notes.