Customers: Moscow Metro Contractors: Optima Transport Product: Complex projects of creation of the engineering systemsProject date: 2016/01
|
Content |
On October 29, 2014 the Optima Transport company announced the project of construction of customs points at the Troparevo station by request of Moscow Metro.
Project Results
Within technical specifications the company created projects of customs points at the Troparevo station. Complexity in the project: the station is new, and customs points had not to be entered in a ready image of the station, and it was required to prepare projects prior to construction.
2016: Upgrade of management of power supply of Mitino electrodepot
On February 16, 2016 the Optima Group announced the beginning of the project of integration of a complex of automated management of power supply of Mitino electrodepot of Moscow Metro.
The project will execute Optima Transport.
Works in the project
In the project it is necessary to use a complex of the technical means developed by Optima Transport and released according to the certificate of conformity. During the project specialists of the contractor should execute installation of the automated jobs in the dispatching center of the Arbat and Pokrovsk line, to execute equipment checkout on two substations of depot and in the dispatching center.
The Optima group stopped being only the system integrator long ago and performs at the different vertical markets also as vendor. We consider the fact that our developments find application in Moscow Metro as high appreciation of our work. Andrey Shandalov, chairman of the board of directors of Group
|
Upon completion of the project the customer will have an opportunity to manage power supply of substations of depot remotely or locally. Need of presence of the round-the-clock persons on duty on substations will disappear.
The Optima group already implemented several important projects on objects of Moscow Metro under construction, generally it is works on design of the systems of automatic equipment and telemechanics of train service, the systems of traction power supply, integration of video surveillance systems and others. We expect that the current project will also be successfully complete and will serve case of improvement of work of the subway. It is especially pleasant that the contractor proposes own solution and the equipment that we consider important in the context of import substitution policy. Vladimir Moiseyev, adviser to the chief of Moscow Metro for capital construction
|
Participants the project are going to complete the works in the coming months.