Project

United Metallurgical Company implemented a production scheduling system

Customers: United Metallurgical Company (UMC)

Contractors: LOGIS (HER LOGIS)
Product: JDA Factory Planner (i2 Factory Planner)

Project date: 2010/06

On August 19, 2015 it became known of signing by the United Metallurgical Company (UMC) and LOGIS company on June 1, 2010 of the agreement according to which LOGIS will deliver and will implement the system of the innovation planning of productions of three of six enterprises of group: OAO Vyksa Pipe Plant, OAO "Almetyevsk Pipe Plant", Foundry and Rolling Complex.

Project Tasks

"The purpose of OMK – to become the most effective producer of pipes of large and small diameter in the Russian market", – Alexey Sdobnikov, the director of supply chain management of OMK noted. - Competitive pressure constantly increases in our industry. We should increase continuously production efficiency and to be for our customers a flexible and reliable supplier with a short cycle of execution of orders. The project on implementing solution on the innovation planning continues the long-term strategy of OMK directed to improvement of quality of customer service and increase in efficiency of activity of the enterprise".

OMK, 2013

In 2009 the implementation project of a system of mid-term planning on the basis of the module SCP from i2 Technologies company came to the end. The solution is used for monthly settlement of the balanced sales plans, production, transportation for pipe products, railway wheels, products of sheet-rolling production. In SCP the need for supply with raw materials is calculated.

The implemented solution helps to estimate quickly different scenarios by drawing up and adjustments of annual and quarter budgets, to estimate the needs for money and to calculate the sales volume and the need for purchases.

In 2010 the company started implementation of processes of the centralized production planning of orders on the basis of the solutions Factory Planner of i2 Technologies company. The project is directed to coordination of activity of divisions of sale, purchases and production for reliability augmentation of accomplishment of orders of consumers.

Implementation of the innovation production planning will help to reduce a cycle of execution of orders without increase of raw material stocks, a WIP and finished goods. Process automation of planning of orders is relevant also in connection with commissioning in 2011 of new rolling mill 5000 in Vyksa that will lead to complication of production routes.

"The supplier and the solution were selected very carefully and responsibly, – Alexey Sdobnikov emphasized. – Eventually, the best was selected that exists now in the world".
"We are glad that we have an opportunity to use our know-how and technologies of the innovation planning at such large producer as OMK", – Dalibor Konvichka, the CEO of LOGIS company told. - We can note with satisfaction that in OMK the specialists having experience with the systems of the class APS work: a few years ago the company was engaged in implementation of modules of mid-term planning from i2 Technologies company. In the field of the innovation production planning of OMK, undoubtedly, is a pioneer among the Russian industrial enterprises. For the project in OMK we selected our best specialists".

Project Results

Implementation time - according to the agreement, the press service of integrator reported. A system is used at the OMK enterprises: VSW, Trubodetal.

Since 2011 the LOGIS company renders to the customer of a technical support service.