RSS
Логотип
Баннер в шапке 1
Баннер в шапке 2
Project

As Mosgortrans created SCS

Customers: Mosgortrans, SUE

Product: SCS projects and wireless network infrastructure

Project date: 2015/05  - 2015/07

On September 25, 2015 the Tegrus company announced project implementation on development and installation of the structured cabling system (SCS) in three divisions SUE Mosgortrans.

Project Results

During the SCS project three objects are equipped:

  • administrative building,
  • building of the station,
  • building of protection SUE Mosgortrans.

Exposure SUE Mosgortrans (2014)

In premises jobs with the corresponding infrastructure are organized, on each of which are set on two RJ45 sockets and on two electric sockets ~ 220B (38xRJ45, 73x220B). For laying of a cable system in buildings are used the Legrand cable channels. Providing requirements of electromagnetic compatibility different routes for low-current and power cables by means of installation of a dividing partition are provided in a cable channels.

The switching centers servicing SCS are developed in the building of administration and in the building of the station, by means of racks on 22U and 6U respectively.

Communication between buildings is provided by the trunk subsystem organized using a cable of the sixth category U/FTP for installation out of premises. At cable laying the available poles on buildings of administration and the building of the station are involved, the rack for connection of the building of protection is specially designed.

Certification of a cable system on compliance of category 5e according to the international standard TIA/EIA 568-B is made.