Far Eastern Distribution Network Company (FEDNC) (Complex projects of service of the engineering systems)
Customers: Far Eastern Distribution Network Company (FEDNC) Contractors: Smartengineering Product: Complex projects of creation of the engineering systemsProject date: 2012/03 - 2012/09
|
In April, 2012 in Vladivostok the construction is completed and the substation (PS) Eagle - an object of DRSK branch of JSC "Seaside electric networks" is put into operation. The project was executed by Smartengineering group.
Project Tasks
The project provided start of PS of 110/35/6 kV Eagle to the APEC summit in September, 2012.
Project Results
Within the project the Smartengineering group performed a complex of works from delivery before commissioning of the capital equipment of telemechanics (RC OF "Iset"), relay protection (NPP EKRA LLC) and antiabnormal automatic equipment (PRO-SOFTWARE). Delivery and works on supervision of erection of the equipment of multiplexing of KEYMILE UMUX 1500 are performed.
List of stages of the project:
- project works on making changes in documentation regarding the equipment of a system of relay protection;
- check of appearance and completeness of the equipment;
- construction and commissioning;
- setup of the equipment, check by a working current and tension;
- individual and comprehensive tests with drawing up test sheets;
- complete instructing of service staff of DRSK branch of JSC "Seaside electric networks" in work with the integrated equipment and in elimination of possible malfunctions.
As a result of the carried-out works of PS of 110/35/6 kV Eagle is delivered under tension in April, 2012.