Customers: Aznakayevskneft Contractors: Krug, NPF Product: PTK KRUG-2000Project date: 2005/03 - 2005/11
|
On February 24, 2016 the Krug company announced completion of project works on modernization of a subsystem of antiabnormal protection (PAZ) of the block of stabilization of oil of installation of complex preparation of oil of NGDU Aznakayevskneft.
Project Task
Oil and gas production department Aznakayevskneft works as structural division of PJSC Tatneft.
For the purpose of execution of the instruction of Rostekhnadzor in NGDU Aznakayevskneft made the decision to retrofit the oil stabilization block additional shutoff valves which will allow to disconnect it from the technology scheme of the platform UKPN in case of exceeding of parameters of the set settings. For reliability augmentation of the developed system PAZ of the block of stabilization 100% "hot" reservation of controllers are provided in the project.
Project Results
KRUG company carried out implementation of an APCS of installation of complex preparation of oil Aznakayevskneft on the platform of the PTK KRUG-2000 software and hardware complex in 2005.
A system provides complete solution of tasks of control, management, protection and diagnostics of technology equipment, long trouble-free operation of the equipment and operation.