Project

In Adygea the region's first solar power plant is constructed

Customers: Administration of the Republic of Adygea

State and social structures

Product: Complex projects of creation of the engineering systems

Project date: 2019/11  - 2020/03
Project's budget: 950 000 000 руб.

2020: Completion of construction of the Adygei SES

On April 2, 2020 the Hevel group announced construction of the Adygei SES with a total power of 4 MW end. The settlement volume of annual production of electrical energy will be 5,132 million kWh.

Completion of construction of the Adygei SES

Works on a construction of the region's first object of solar generation began in November, 2019 and according to the diagram were complete in March, 2020. For April 2, 2020 on SES balancing and commissioning, supply of electricity in network are conducted the power plant will begin in May, 2020.

In the republic construction of one more solar power plant - the 4.9 MW Shovgenovsky SES is conducted. An object will be put into operation in the fourth quarter 2020.

Completion of construction of the Adygei SES

The agreement on construction of two solar power plants in the Republic of Adygea between Hevel and the government of the region was signed in 2018. Investment volume of the company into construction of two stations will be more than 950 million rubles.