Ventall participates in the construction of the TPP Nezhinsky GOK in Belarus

Customers: Slavkaly

Minsk; Mining



Project date: 2021/02  - 2021/07

2021: Construction of the start-up complex of the CHP of the Slavkalia concentration plant

On September 6, 2021 Russian , the metal structure manufacturer "" announced that Ventall it was taking part in one of the significant construction projects of the Republic - Belarus the Nezhinsky GOK. For constructions the start-up complex COMBINED HEAT AND POWER PLANT of the "" enrichment plant, Slavkaly the supply of the first stage of galvanized professional steel in the amount of 3,550 linear meters and 3,000 square meters. m of wall sandwich panels with polymer coating PVDF was completed. Production and the shipment of materials is carried out Tula production by the Ventall Group of Companies site - the plant.Di Ferro

This is the third manufacturer project implemented for Slavkali. Nezhinsky mining and processing plant has been under construction since 2016, and the construction of auxiliary CHP 38 MW was the next stage of construction. Di Ferro is involved in the project both as a supplier of metal products and as a designer. In The tasks of the manufacturer's design bureau included the development and design of KMD drawings necessary for the manufacture of enclosing structures:

  • coatings and slabs made of profiler;
  • walls and partitions of sandwich panels.

The project was developed on the basis of regulatory documents and technical requirements, which were provided by the contracting organization, which performed the design of all facilities of the potash complex.

A distinctive feature of this order was the use of sandwich panels with a PVDF polymer coating with an increased thickness of 40 microns versus standard 25-30 microns. This design choice was due to the features of the operation of the launch complex building. A booster compressor station, a generator switchgear, a gas turbine and a diesel generator plant will be installed here, which implies strict conditions for influencing the structure due to environmental aggressiveness. The PVDF polymer coating is one of the most resistant to any non-mechanical effects, and the increase in its thickness has further increased the protection of sandwich panels from external effects. As a result, the performance of the structure was improved.

In total, three stages of construction of a thermal power plant are planned. At the beginning of September 2021, the construction of the first launch complex was completed, equipment was being installed. The commissioning of the complex is scheduled for the third quarter of 2021, after which Ventall Group will continue to supply metal products.

File:Aquote1.png
"The total estimated volume that we plan to produce and ship for the construction of the CHPP of the Nezhinsky concentration plant is 10,000 square meters. m of sandwich panels and 14 00 ppm of profiled flooring. The production capacity of our plant allows us to master such a volume in a short time, and we will timely fulfill our obligations to the contractor, "-

said Sergey Meshcheryakov, manager of key clients of Di Ferro.