Project

RusHydro (1C: Consolidation)

Customers: RusHydro

Moscow; Power

Contractors: MKSKOM
Product: 1C: Consolidation

Project date: 2012/04  - 2012/09

2012: Creation of AIS for monitoring and control of construction and repair subsidiaries

Prerequisites for the creation of AIS MIK

  • Increase in repair and construction work
  • Need for detailed detail for management
  • Need for prompt access to construction progress information
  • The need for operational control to improve the efficiency of investment programs

Project Objectives and Objectives

Purpose:

Typification and streamlining of financial and economic management processes in the S/S performing the functions of the General Contractor/Contractor for construction, installation, design and repair works.

Tasks:

  • Create a sample solution that includes:
    • FEU and accounting methodology (process procedures, control procedures and accounting standards)
    • AIS on the basis of 1S:USO for solving the tasks of operational accounting and control in SIS/IC and for solving the tasks of consolidation and management within the holding (together with the developer of AIS)
    • procedures for integration interaction with related information systems
    • NSI organization

  • Implementation of a standard solution at the facilities
  • Creation of a control environment - related end-to-end control processes at all levels of management, with the aim of a qualitatively new level of management decision-making

Decision

Project results

As a result of the project implementation, an automated information system was created to monitor and control the activities of repair and construction S/S on the basis of 1C: Consolidation 8 PROF (AIS MIK).

AIS MIC consists of the following units:

  • SDA/SDA cash consumption control Block. Includes formation and approval of payment/tranche request registers and their control
  • Block for collecting and preparing information of SW/SW. Includes tools for collecting, generating and analyzing data on monitoring the activities of SW/SW

Key success factors for the project:

  • Personal interest of senior management as a result of
  • Well-coordinated team
  • Unification and standardization of the methodological base

Implementation milestones:

  • Quick start collecting data into Excel layouts
  • Work to improve the quality of the data provided
  • Enterprise Accounting System Template Deployment in S/S
  • Readiness to overcome resistance to changes in SW