Customers: World Trade Center (TsMT Moscow) Moscow; Tourism, hotel and restaurant business Contractors: Croc Product: Complex projects of creation of the engineering systemsProject date: 2010/09
|
The CROC company and JSC World Trade Center (WTC) completed the engineering project unique in terms of the scope of. For only one over a year in a complex of buildings of the second queue TsMT-2 consisting of the 30-storey office building ("Office building-3"), 20 floor club body of Crowne Plaza Moscow WTC hotel and 4 the-level closed parking the full range of the systems of power supply is implemented.
The Moscow World Trade Center is the first business center of Russia and the largest in the territory of Eastern Europe. All objects of the second queue of TsMT-2 were equipped with forces of specialists of CROC company the systems of power supply, including outside and internal power supply, transformer substations.
"The project was at the same time interesting and difficult. First of all — on the scales: only one electric cable more than 50,000 meters were laid. Daily more than one hundred mounting workers were necessary to organize work, to be coordinated with 20 adjacent contract organizations. However terms were sustained. Now there is a new stage — the equipment of power supply systems and automation of the new administrative building of TsMT" — the director of the department of intellectual buildings of CROC company Shirokov Alexander commented on completion of works.
In turn, the first deputy head of Directorate of object TsMT-2 under construction Askhat Yusupov noted: "For us objects of new office hotel complex are priority. Their design and construction was led taking into account the highest quality requirements, including — to reliability of the engineering systems of buildings. All technical solutions on power supply of a complex are implemented using the high-class equipment and with observance of all environmental, sanitary and fire protection regulations".