Companies "National Project" digitalize the objects of the new Trinity line "Moscow Metro"

Customers: Moscow Metro

Moscow; Transport

Product: Elteza MPC-EL

Project date: 2021/04  - 2023/12

2024: Plan for the introduction of automation at the facilities of the Troitskaya line under construction

The movement of trains at the facilities of the Troitskaya line of the Moscow metro under construction will be controlled by digital automation of the development and production of the Railways Division of the National Project. This was announced by the 1520 Group of Companies on September 26, 2024.

source = 1520 Group of Companies

Metro train intervals are shorter than on the railway, and passenger traffic is more intense. Digitalization ensures the safety of transportation with high line load.

Automation for the subway is protected from dust, moisture and voltage drops, this guarantees high reliability of systems. Hot redundancy of all electronic components and duplication of data transmission channels are provided.

Microprocessor centralization, a digital interval control system for train traffic and digital power plants will be installed at the Akademicheskaya, Vavilovskaya, Krymskaya, ZIL and Kommunarka - Novomoskovskaya stations. Systems process information from floor devices at maximum speed and transmit it to the dispatcher's computer. Personnel can remotely adjust arrows and traffic lights, diagnose equipment, set train routes. High speed increases the parity of trains on the line and reduces traffic intervals.

During the work, the specialists of the National Project companies will mount post devices, lay cables, install tunnel equipment and commission the systems.

2023

Equipping the Aminyevskoye electric depot with the MPC-EL system

On January 9, 2024, Moscow Mayor Sergei Sobyanin commissioned the Aminyevskoye electric depot, which was specially built to service the BCL. Digital automation of the ZHAT GK 1520 Division will control the movement of trains in one of the large depots of the Moscow metro .

The depot introduced a micro-centralization system processor MPC-EL with built-in cyber protection, digital rail circuit control modules and modular power plants, installed electric switches.

Digital systems of domestic development and production will regulate the operation of arrows and traffic lights, monitor equipment parameters, diagnose and identify pre-failure conditions.

Commissioning of the Aminyevskoye electric depot will increase the number of mobile units at the BCL and the line capacity. With such heavy traffic, digitalization will ensure the safety and reliability of transportation.

Earlier, the ZHAT GK 1520 Division digitalized traffic control in two other BCL electric depots: Nizhny Novgorod and Zamoskvoretsky.

Start of works on installation of train traffic control systems at Potapovo station

Specialists USC 1520 (part of GK 1520) began installing train traffic control systems at the Potapovo station under construction and the Potapovo-Kommunarka section of the Sokolnicheskaya line of the Moscow metro. This was announced on October 23, 2023 by representatives of the Group of Companies 1520.

The facility will introduce the Russian automation for the development and production of the ZHAT GK 1520 Division. The micro-centralization system processor for MPC-SM subways will regulate the intervals between trains. Also, the station will install modern floor rail circuit devices and stationary equipment.

Taking into account the specifics of the metro, the developers have provided for hot redundancy of all electronic components of the traffic control system. This ensures high reliability and increases the security of critical infrastructure. For stable operation, all digital equipment is protected from dust and moisture. In addition, the system has built-in protection against cyber attacks from external data networks.

Thanks to digitalization, metro personnel will be able to more effectively control arrows and traffic lights, control equipment parameters and quickly draw up routes.

Earlier, in 2019, GK 1520 installed automation on the Salaryevo-Kommunarka section of the Sokolnicheskaya line, in 2023 it digitalized the Koltsevaya line of the Moscow metro and BCL facilities.

The construction of the Potapovo station is carried out by Roads and Bridges JSC (part of the National Project Building). It is assumed that the station will improve transport services for residents of the Novomoskovsk district and the Yuzhnoye Butovo district. The launch of the Potapovo station is expected in 2024.

Plan for installation of alarm, centralization and interlock system at Potapovo station of Sokolnicheskaya line

USC 1520 (part of GK 1520) on April 12, 2023 announced that it would install alarm, centralization and blocking systems at the Potapovo station of the Sokolnicheskaya line of the Moscow metro.

The station will be equipped with Russian automation, which will ensure the optimal interval and safety of train traffic, control over the operation of equipment.

In particular, digital equipment for the development and production of the ZHAT GK 1520 Division: a system of rail circuits and power plants will be installed at the facility.

The works are performed on a turnkey basis - from the supply of equipment and materials for the entire complex of works to pre-commissioning and commissioning.

The Potapovo station of the Sokolnicheskaya line will significantly improve transport services for almost 70 thousand residents of the Novomoskovsk district and the Yuzhnoye Butovo district.

Equipment Plan for All Large Loop Stations with Digital Modular Feeder Units

The ZHAT GK 1520 division will provide digital automation systems of its own design and production of all stations and the electric depot of the large ring line of the Moscow metro. About this GC 1520 reported on March 1, 2023.

All BCL stations are equipped with digital modules for monitoring rail circuits, as well as digital modular power plants. A microprocessor centralization system MPC-EL with built-in cyber protection is introduced into the electric depot.

Taking into account the specifics of the subway, all equipment is protected from dust and moisture. Redundancy of components and data links ensures high reliability of systems.

Russian automation will regulate arrows and traffic lights, monitor equipment, conduct diagnostics, detect pre-failure conditions, and control the arrival of rolling stock at the depot for maintenance.

With the launch of the BCL, the digital systems of the LAT Division will ensure the reliability and safety of transportation during heavy traffic, and will increase the reserves of line throughput.

Introduction of digital automation in the Nizhny Novgorod electric depot

GK 1520 equipped the Nizhegorodskoye electric depot with digital Russian automation, which will serve up to 40% of the composition on the Big Ring Line of the Moscow Metro.

File:Aquote1.png
A feature of the metro is heavy traffic and large passenger traffic. Trains here run at much smaller intervals than on the railway. Digital control systems will ensure the reliability and safety of transportation with high line load, - said Konstantin Khromushkin, Deputy General Director for Innovative Development and Digital Transformation of the Group of Companies 1520.
File:Aquote2.png

Microprocessor systems for the development and production of the ZHAT GK 1520 Division will control the arrival of rolling stock in the depot for maintenance, regulate the operation of arrows and traffic lights, monitor equipment parameters, diagnose and detect pre-failure conditions.

The electric depot installed a microprocessor centralization system MPC-EL with built-in cyber protection, digital modules for monitoring rail circuits, as well as a digital modular feeder. Redundancy of components and data transmission channels guarantees high reliability of automation. Taking into account the specifics of the subway, all equipment is protected from dust and moisture.

Trains of the Big Ring Line will serve three electric depots: Zamoskvoretskoye, Nizhegorodskoye and Aminievskoye. The movement at all three facilities will be controlled by digital automation of the development and production of the ZHAT GK 1520 Division.

The Nizhny Novgorod electric depot is located in the Lefortovo area on the site of the Moscow plant for the modernization and construction of railcars named after Voitovich. The total area of ​ ​ objects exceeds 17 hectares - these are more than 50 buildings and structures, including a sedimentation and repair building for 30 trains, etc. Up to 288 cars a year will be repaired here.

Introduction of Russian digital automatic ring line

The 1520 group of companies in January 2023 announced that the specialists of the railway automation and telemechanics division (ZHAT) and the United Construction Company 1520 (USC 1520), which is part of it, reconstructed and equipped the ring line of the Moscow metro with digital Russian automation.

The ring line of the Moscow metro opened to passengers on January 1, 1950. The line includes 12 stations, the operating length is 19.4 km. The total length of auto-blocking (295 rail chains) is 38.8 km. The minimum intercity interval is 90 seconds.

Outdated relay devices on the ring line were replaced with digital ones "(photo - russos.livejournal.com)"

Instead of the outdated relay devices of 1954, the GK 1520 specialists installed modern microprocessor systems for monitoring rail circuits, microprocessor centralization, dispatching and automatic diagnostics on the ring line.

Rail chains are a means of monitoring the freedom of track sections and the integrity of rail threads, as well as transmitting signal readings from the way to the train. Microprocessor centralization system - an automated process control system that controls the operation of equipment (arrows, traffic lights, etc.), monitors and optimizes train routes, monitors equipment parameters, detects pre-failure states, etc.

GC 1520 explained to TAdviser that modern microprocessor automation for the development and production of its LAT division was introduced. These microprocessor systems make the most of Russian microelectronics, especially in the most critical nodes, the company says.

The new equipment, according to the developers, will reduce the intervals between trains by 10-14%. During rush hour, 36 pairs of trains will be able to pass along the line instead of 34, it will become freer in the cars.

It is also expected that metro personnel will be able to more effectively control arrows and traffic lights, control equipment parameters, draw up routes faster and regulate traffic schedules.

File:Aquote1.png
The Moscow Metro is one of the busiest in the world. The network of lines is continuously developing due to the construction and modernization of infrastructure, passenger traffic is growing. With high traffic intensity, the latest digital control systems will ensure the reliability and safety of transportation, guarantee uninterrupted operation of equipment, "says Konstantin Khromushkin, Deputy General Director of GK 1520 for innovative development and digital transformation.
File:Aquote2.png

After the modernization, the nature of threats to relay devices changed. So, for old relay systems and devices, threats such as the influence of the human factor, the absence of self-diagnostics, etc. But computer systems are already used to control relay devices, for which the issue of cyber threats is relevant, TAdviser explained in GC 1520.

File:Aquote1.png
The microprocessor centralization of the MPC-EL, installed on the ring line of the metro, has a built-in cyber defense system, which completely excludes unauthorized access to critical infrastructure, the company says.
File:Aquote2.png

During the reconstruction, new power equipment of traction substations of the ring line was also installed for reliable power supply to automation. Wire communication networks, fire and security alarm systems with automatic gas fire extinguishing, ventilation and air conditioning were reconstructed.

The specialists of GK 1520 performed most of the construction and installation work without stopping the line. Only for the time of equipment switching did it take to partially change the train pattern.

The digitalization of the metropolitan metro began in April 2021. Then the specialists of the ZHAT GK 1520 division installed their own microprocessor centralization system in the Sokol electric depot. This was the first experience in introducing its microprocessor centralization in the Moscow metro.

File:Aquote1.png
Currently, we have signed a contract for the introduction of modern microprocessor systems at new construction facilities in the Aminyevskoye and Nizhegorodskoye electric depots, - told TAdviser in GK 1520.
File:Aquote2.png