Gazprom completes equipment by a communication equipment of objects of the Sakhalin-Khabarovsk-Vladivostok gas pipeline

Customers: Gazprom

Moscow; Gas industry

Contractors: Lanit-Partner
Product: Complex projects of creation of the engineering systems

Project date: 2012/01  - 2012/11

Content

The LANIT-PARTNER company completed installation of equipment of communication on the Sakhalin-Khabarovsk-Vladivostok gas pipeline, the press service of the company reported on November 19, 2012. General customer of JSC Gazprom.

Start of Project

LANIT-PARTNER of the beginning cooperation with Gazprom in April, 2011. For implementation of this project in the company the special directorate is created, the staff of engineers and volume of technical means significantly grew.

Implementation

Specialists LANIT-PARTNER mounted a communication equipment on 64 objects of the Sakhalin-Khabarovsk-Vladivostok gas pipeline (1400 km).

The active phase of installation works began in 2012 when on all objects of the gas pipeline construction readiness was reached. Installation and construction works are performed within six months then specialists of the company started setup of the equipment.

Technical solution

On the gas pipeline two types of communication are used: radio relay NEC DMR 5000 and mobile the TETRA standard from Selex company. Installation and setup of the equipment were executed by specialists LANIT-PARTNER according to the approved diagram of conducting works.

Murad Tagirov, director of the department of telecommunications, power and LANIT-PARTNER transport: "This project by right can be considered one of the most large-scale and significant telecommunication projects of the company. During its implementation we got absolutely new experience on the gas pipeline, qualification of our specialists who successfully mounted and set up the equipment of the most modern type considerably grew. Engineers of the company once again proved the professionalism as all works were performed up to standard and at the scheduled time, despite remoteness and inaccessibility of the majority of objects".