DPC of DataPro Tver

Product
Developers: RT-Invest Transport Systems (RTITS)
Date of the premiere of the system: October, 2013
Technology: DPC

Content

The data center of the Tier III level was designed and constructed from the moment of the beginning of design (on February 15, 2013) before start in operation (on October 16, 2013) in 8 months. Power supply according to scheme 3/2N was implemented and certification is undergone in an effect and the certificate (12/12/2013) on compliance of the project solution to the Tier III Uptime Institute level is treated Was own solution on moistening of air in machine halls based on the adiabatic principle is implemented.

The first data center of DataPro company in Tver received at the end of 2013 the certificate of Uptime Institute of level of fault tolerance Tier III in category Design. The project solution allows to place 400 racks with a power consumption from 7 kW. Installed capacity of an object is 4.5 MW; The Data center is put into commercial operation in November, 2013.

2015

the Data center replaced the owner

On March 18, 2015 more than 12 t[1] became known of acquisition of DPC of "DataPro Tver" by "RT-Invest Transport Systems" company for creation of Command center and monitoring of a system of collection of a payment from cars[1].


"DPC of DataPro Tver", 2014


The new owner books audit of subsystems of the center with involvement of specialists.

For March 19, 2015 project works on opening of TsUiM by the time of start of a system in operation are conducted. It is appointed to November 15, 2015.