Federal State Institution "Nalog-Service" UFNS across the Nizhny Novgorod Region upgrades server DPC
Customers: Tax Service of Federal State Institution of UFNS across the Nizhny Novgorod Region Nizhny Novgorod; Government and social institutions Contractors: I-Teco (iTeco) Product: Complex projects of creation of the engineering systemsProject date: 2013/08 - 2013/12
|
On December 19, 2013 the I-Teco company announced project completion on creation of engineering infrastructure of the additional server premises of FTS branch Federal State Institution "Nalog-Service" in the Nizhny Novgorod Region.
Project Tasks
"In a portfolio of our company – a number of large-scale projects on deployment of business and critical, geographically distributed and virtual environments for large Russian customers, the organizations of monitoring and management business and IT infrastructure and also to implementation, maintenance and integration of information systems. In addition, specialists of the company have wide practical experience and examination in the field of design and construction of modern data centers. All this allowed I-Teco to win electronic biddings, and UFNS across the Nizhny Novgorod Region – to receive the reliable contractor for implementation of this project, – Vladimir Shchetinin, the director of Development center of infrastructure solutions of I-Teco company noted. – The task to quickly design and implement complex failsafe infrastructure of FTS branch Federal State Institution "Nalog-Service" in the Nizhny Novgorod Region which opportunities include flexible scaling was set for us".
Project Progress
The computer system deployed by I-Teco by request of Office of the Federal Tax Service in the Nizhny Novgorod Region included:
- The systems of regular power supply, conditioning and ventilation, automatic gas fire fighting for the additional server premises.
- Security solutions with video surveillance, control and access control and the security fire warning.
- Basis for deployment of the centralized automated system of supervisory control.
Within the project comprehensive examination of bearing capacity of the base and overlappings of the building is conducted, also the analysis of the existing power supply system of branch Federal State Institution "Nalog-Service" is audited. The team of specialists of I-Teco carries out works on design and installation of engineering infrastructure of data center, the necessary equipment is supplied, transformer substation is reconstructed and also switching of consumers for optimization of a power consumption and increase in fault tolerance is provided.
"On behalf of Office of the Federal Tax Service in the Nizhny Novgorod Region I thank I-Teco company for creation of scalable and failsafe engineering infrastructure of data center. All project team members proved as high quality professionals who can do accomplishment of the most uncommon tasks even in the conditions of tight temporary restrictions, – Sergey Malyshev, the deputy manager of FTS across the Nizhny Novgorod Region emphasized. – The project was implemented according to technical specifications, completely satisfying our current demands and expectations. Now the new server hall of DPC of branch Federal State Institution "Nalog-Service" in the Nizhny Novgorod Region is successfully put into commercial operation".