Customers: Vostokgazprom Contractors: Tops Consulting Product: Microsoft Dynamics AX 2009На базе: Microsoft Dynamics AX Project date: 2013/04 - 2014/02
|
On February 12, 2014 it became known of implementation of the new version of Microsoft Dynamics AX in Vostokgazprom company. Works in the project were carried out by Tops Consulting company.
Project Tasks
Before as the main IT system of management the group used two applications on the basis of the ERP system of Microsoft Axapta 3.0 — separate installations for Vostokgazprom and Tomskgazprom companies (subsidiary company). Existence of two systems did not facilitate creation of the summary reporting under group, complex systems of synchronization of data between the companies and applications, non-standard registers of settlement and comparisons were required that caused additional load of employees.
The management of Vostokgazprom saw development and a basis for further growth in accumulation of speed of providing information for decision making by managers of the company, cost optimization on IT due to consolidation of bases and applications of all economic entities, creation of uniform IT space for support of business and providing high-quality service to users.
Tops Consulting and Vostokgazprom faced a joint project team a task - to save the available practices in the field of business process automation of the company and to increase, relying on opportunities of the new version of the Microsoft Dynamics AX system.
Project Results
As a result of execution of the project the speed and performance of the ERP system is increased, its functionality is expanded, key business processes are optimized.
A new system on the Microsoft Dynamics AX platform provides with technology support the key directions of financial and economic activity of Vostokgazprom. By means of the created solution management of investment programs, monetary to means, is implemented by stocks, receivables and payables, planning of budgets, property, financial accounting.
"In a project deliverable we considerably accelerated many processes in the company and were provided with convenient tools for obtaining the operational reporting and the analysis of financial data — Vladimir Kalyuta, the head of department of the budget and calculations of Vostokgazprom company told. — The fact that users of a system noted 30% fall forward of reporting and more user-friendly interface of a system is pleasant".
"The project is executed in the shortest possible time and within the budget — Andrey Saraykin, the head of department of information technologies of Vostokgazprom company commented on project deliverables. — We could achieve significant economy thanks to optimization of IT applications, as much as possible using standard functionality of Microsoft Dynamics AX, our practices and the solutions Tops Consulting".
"We are grateful to our partners for professionalism and the involvement of a command at all stages of implementation and for active support of the project from management of Vostokgazprom company — Alexey Kurochkin, the director of the department of Microsoft Dynamics AX of Tops Consulting company said. — Harmonious joint work Tops Consulting and Vostokgazprom, mutual aspiration to apply the advanced techniques and tools allowed us to solve completely all assigned tasks and to observe the designated time and budget frames of the project".