Customers: 3Data
Contractors: Mastertel (MT Telecom) Product: Master-KonnektProject date: 2014/03 - 2015/09
|
2014
At the end of 2014 the Mastertel telecommunication company connected new data centers of 3Data company to the selected fiber-optical network "Master connection".
At an initial stage of cooperation Mastertel provided to the partner powerful technology base on which 3DATA started a complex of the cloud services demanded in the market. The IT infrastructure organized by specialists of the company helped to optimize internal business processes and increased effectiveness of activity of network of club data centers. Within the new project Mastertel laid a cable of the increased capacity on the basis of which the full range of telecommunication services was provided to the client to new DPCs.
"For network of club data centers the reliable communication is one of key factors. And in combination with engineering of DPC of the Tier III level it allows to provide dynamic development of IT infrastructure for clients of any scale. Cooperation with 3Data - the next step in the strategy development Mastertel based on the solution of business challenges of any complexity with the help of consolidation of own telecommunication opportunities and the partner's opportunities", – Vitaly Ezopov, the CEO of Mastertel company noted.
Ilya Hala, the CEO of network of club data centers 3Data, told: "Start of new data centers is very important and responsible event. For us a priority is ensuring high-quality and smooth operation of any of our objects. We are very grateful to a command Mastertel for the efforts made by them and fine technical support thanks to which it also became possible. It is sure that our effective cooperation with Mastertel company will successfully develop, and together with our partner we will continue to study the next stage of interaction".
2015
The Mastertel telecommunication company connected the data center of "B17" of company 3data located at the address Moscow, Butlerov St., 17 to Master-Konnekt network at the end of 2015. It became the next stage of creation of a big distributed network of DPC based on which the innovation projects are implemented: failsafe solutions for clients, the distributed cloud platforms and the integrated services.
Within the project independent cable entries to new data center were constructed, cables of the increased capacity – up to 264 optical fibers are laid. Now all consumers of IT services of the capital got access to the newest technologies of the highest quality for ensuring dynamic development of the information - infrastructure.