Last Release Date: 2025/06/23
Technology: DPC

Content

Main Article: Data Center (Data Center)


Data center "M8" is positioned as the flagship of the network. 3Data The object is located on the 4th street. March 8, next to the most important fiber-optic highways and is one of the most convenient points for crossing and exchanging traffic in. To Moscow

2025: Modernization of the data center in the northern administrative district of Moscow

The company 3data carried out a planned modernization data center of the M8, located in the Northern Administrative District. Moscow The updated engineering infrastructure has a higher efficiency, which allowed to increase the energy efficiency of the facility and free up about 15% of additional capacity for customers of the equipment placement service (). colocation The company announced this on June 23, 2025.

The modernization of the data center was carried out in stages in order to ensure the continuity of customer business processes. The first stage included an update to the video surveillance and access control system, which made it possible to improve the security of the facility.

The 3data technicians then replaced the uninterruptible power supplies (UPSs). Three new modular UPSs from IMPULSE were installed, each with a rating of 100 kVA. At the same time, the battery arrays from the manufacturer B.B.BATTERY with an increased number of batteries were completely replaced . This allowed to extend the battery life of the equipment up to 17 minutes. The UPS replacement took 3 working days, during the work the data center was powered by electricity from the diesel generator set (DGP), which ensures uninterrupted operation of the facility.

In May 2025, work was carried out to modernize the air conditioning system. As of June 2025, freon pipelines, receivers and external capacitor units have been completely replaced. Also in the next 3-4 months, it is planned to replace internal units by service life. The upgrade of air conditioners is aimed at maintaining reliability and increasing the performance of the cooling system, which will allow you to allocate additional power in favor of the server equipment of customers. The Stulz cold supply system will be replaced with a more productive new generation model.

File:Aquote1.png
The M8 data center was the first object in our network to undergo a global comprehensive modernization. Since its commissioning in 2014, the facility has demonstrated stable operation without significant incidents. This confirms the correctness of the chosen engineering solutions more than 10 years ago. Planned site improvements allow us to significantly increase the technical performance of data centers, taking into account the requirements for fault tolerance and density, - said Maxim Tserulev, technical director of the 3data data center network.
File:Aquote2.png

2016: Tier III Compliance

As of January 2016, the level of engineering systems of the M8 data center met the requirements of the Tier IIIUptime Institute standard.