Project

"The first engineer" executed installation of equipment for "Northwest combined heat and power plant"

Customers: Northwest combined heat and power plant

Power

Contractors: The first engineer
Product: Complex projects of creation of the engineering systems

Project date: 2016/03  - 2018/04

2018: Replacement of circulation electric pumps of boilers utilizers of block No. 1

On June 18, 2018 the company the First engineer announced accomplishment of installation of equipment for needs of branch "Northwest combined heat and power plant" of JSC Inter RAO — Power Generation.

Project Tasks

JSC Inter RAO — Power Generation pays considerable attention to a status of the generating capacities. 20 thermal power stations with a total set electric power of 22.7 GW are its part.

In 2017 the company made the decision on replacement of outdated circulation electric pumps of boilers utilizers of block No. 1 on branch "Northwest combined heat and power plant" for the purpose of reducing costs for expensive repair work.

Project Progress

To exclude influence of works on replacement of the equipment on power consumers, to the contractor – The First Engineer company – the task to carry out installation of equipment in turn to a short time at the station working in the normal mode according to the plan approved by the customer was set.

When implementing The First Engineer project executed dismantling of an obsolete equipment, and then performed construction and commissioning of four circulation electric pumps of high pressure of boilers utilizers of block No. 1. Work was complicated by inaccessibility of the equipment, however the wide experience of a team of "The first engineer" allowed to cope with assigned tasks successfully.

The equipment of Inter RAO is Power generation

Effective interaction of the station and the contractor allowed not only to perform the planned works in time, but also to complete the project ahead of schedule: installation of two pumps was implemented according to the plan, and the planned installation of the remained pumps, thanks to timely providing the equipment by the customer, came to the end practically for half a year earlier.

Project Results

"The first engineer" performed replacement of four circulation electric pumps of high pressure of boilers utilizers of block No. 1 and also cooler of steam and the control valve of a power supply of a boiler of high pressure.

As a result of the made replacement of the equipment the combined heat and power plant will ensure smooth operation and safe operation of boilers utilizers.

2017: Commissioning of a system of ball cleaning of condensers of blocks No. 1 and No. 2

On April 11, 2017 The First Engineer company announced project completion on commissioning of a system of ball cleaning of condensers of blocks No. 1, No. 2 for needs of branch "Northwest combined heat and power plant" of JSC Inter RAO — Power Generation. The First Engineer company took part in the project as the general contractor.

Project Tasks

For improvement of technical performances of the station and optimization of finance costs on service, at Northwest combined heat and power plant decided to implement the system of ball cleaning (SBC) of condensers of blocks No. 1, No. 2.

Northwest combined heat and power plant, (2014)

Project Progress

Within the project specialists of "The first engineer" executed delivery of required materials for Northwest combined heat and power plant, executed construction, commissioning of SShO, tested and prepared an object for commissioning.

Works are carried out by forces of production and mounting division of Pervy inzhener LLC. Existence of own resource allowed the engineering company to perform works in hours, convenient for Northwest combined heat and power plant, in the minimum terms.

SShO at Northwest combined heat and power plant, (2016)

Works are held under control services of quality management, with the participation of engineering groups of The First Engineer company.

Project Results

The performed works helped to provide branch of Northwest combined heat and power plant increase in profitability of steam-turbine installation of St. PT-10, 20, power deceleration, consumed by circulation pumps and to reduce repair operating costs.