Customers: Centrkazenergomontazh (TsKEM) Contractors: Tornado Modular Systems Product: PTK Tornado-N (prototype of the National platform of industrial automation, NPPA)Project date: 2017/11 - 2018/04
|
The Novosibirsk company "Tornado Modular Systems" announced on May 30, 2018 end of the next stage of works on automation of boiler units of CHPP-1 Astana of the Republic of Kazakhstan. As of May, boilers No. No. 3, 4, 5, 6, 7 are automated.
As the customer on the project the Centrkazenergomontazh company (TsKEM) acted, the general contractor, and the designer of the APCS field level of all units at this station is the old partner of Tornado Modular Systems Group — design institute Pavlodarenergoproyekt LLP.
Tasks
As the director of official representative office in the Republic of Kazakhstan Ilya Sorokin told, under the terms of the agreement installation of an APCS on boiler units should be performed in very short time — before the beginning of a heating season, but it is not a problem, specialists of the company had to solve similar problems and earlier.
Project Progress
PTK for an APCS of boiler No. 6 is shipped at the end of 2017. In the first quarter 2018 adjustment of the top level of an APCS is finished, a system is put in trial operation.
Works for CHPP-1 will be continued — the agreement on design and delivery of PTK for an APCS of fuel feeding and boilers No. No. 1, 2 is signed.