Customers: UEC-gas turbines (UEC-GT) Rybinsk; Mechanical engineering and instrument making Contractors: Sinto Product: Complex projects of creation of the engineering systemsProject date: 2017/08 - 2017/12
|
On July 12, 2018 the Sinto company announced carrying out electric installation work on 4 gas turbine units of JSC ODK-Gazovye turbiny. In 2017 JSC ODK-Gazovye turbiny signed the delivery contract of 6 GTA-6RM units for the second queue of gas turbine power station on the Yurubcheno-Tokhomskoye field, PJSC Rosneft.
Within the general project on production of gas turbine units before Sinto company there was a problem of accomplishment of electric installation work on different nodes of GTA-6RM units with a rated power of 6 MW everyone. GTA-6RM units are manufactured in block and container execution with an opportunity for work on two types of fuel (associated petroleum gas and diesel fuel). As the power unit gas turbine GTD-6RM drives of production of PJSC UEC Saturn are used.
Within the project, from August to December, 2017, electric installation work on GTA-6RM units is performed:
- Wiring of the block module SCD
- Wiring of electric heaters of the block module SCD
- Wiring of lighting on a roof of the block module SCD
- Gas metering wiring
- Wiring of the sensor of gas contamination of SO
- Wiring of the block module of the turbine generator
- Wiring of a ventilation system of container TG
- Wiring of the TK-6 turbine generator
- Wiring of the block of power block and container GTA-6RM
- Wiring of block and container GTA-6RM.
The Sinto company noted that warranty obligations make 36 months. If during warranty operation of results of works the defects interfering normal operation are found, the Contractor is obliged to eliminate them at own expense in the terms coordinated with the Customer.
"The gas turbine unit is the difficult engineering device equipped with a large number of the different systems. Depending on execution the players of a set can be changed – to be supplemented with a wide number of the option equipment. However irrespective of a complete set the production process of the unit in itself represents difficult and multi-stage process at which all stages quality requirements of production, to installation and a commissioning are placed. Despite delays in execution of works at separate stages, finally all terms according to the supplementary agreement were observed and the works are completed in time and in full". Dmitry Alekseyevich Solovyov, the head of Directorate on production of JSC ODK-Gazovye turbiny |