Rostelecom installed almost 90,000 smart electricity meters in the Perm Territory

Customers: Rosseti Ural (IDGC of the Urals)

Contractors: Rostelecom
Product: ASCUE projects

Project date: 2018/04  - 2018/07

2022: Installation of 90,000 smart power meters

Rostelecom on April 18, 2022 announced that in four years it installed almost 90,000 smart electricity meters in the Perm Territory. About 70,000 meters were integrated by the company's employees at the first stage of the project - from 2018 to 2020. Another 20,000 metering devices were installed by the beginning of 2022, thus completing this project. The work was carried out as part of a contract with Rosseti Ural.

According to Rosseti UralsPermenergo Alexander Shagov, Deputy Director for the Development and Sale of Services of the "" - "branch, modernization of electricity metering systems is one of the important elements of digital transformation housing and communal services.

Шаблон:Quote 'author = said Alexander Shagov, deputy director for the development and sale of services of the Rosseti Ural branch - Permenergo.

Шаблон:Quote 'author = noted Peter Kozlovsky, Director of Perm Branch of PJSC Rostelecom.

2018: Pre-design survey of electrical network facilities

The project operator - PJSC Rostelecom"" - within the framework of the implemented energy service contract concluded with OJSC "," IDGC of the Urals completed a pre-design survey of electric network facilities in the summer of 2018. According to the results of the survey, Rostelecom specialists developed a scheme for organizing and modernizing an electricity metering system with remote collection and storage of data, determined technical solutions for installing and adjusting the metering system, and formed design documentation with targeted binding of typical versions of installing electric metering devices. In total, more than 35 thousand electricity metering units were examined, both for household consumers and legal entities. The survey was carried out by 14 brigades in the Krasnokamsk, Ilyinsky, Dobryansky, Kungursky, Estrisk, Perm regions of the region and in the city. Perm

The next stage is construction and installation work and the integration of new metering devices into the already existing system. The project is planned to be fully implemented by the end of the 1st quarter of 2019. The new modern equipment will reduce the loss of electric energy, reduce unaccounted consumption, improve the quality of power supply to consumers by eliminating third-party interference in the network, and stimulate energy-saving behavior among consumers.

"Our specialists will ensure complete protection of information from leakage and unauthorized access. A special coded system for identifying users and transmitting data over the network will be installed. The company performs all the work at the expense of its own investments, and the costs will be paid off by the savings received after the introduction of energy-saving solutions, "comments Roman Sandalov, director of the Perm branch of Rostelecom PJSC.
"The project, which we are implementing together with Rostelecom, enters an active phase related directly to the installation of new, intelligent metering devices," said Yuri Belozertsev, deputy director of the branch of IDGC Ural OJSC - Permenergo for the development and implementation of services. - Plans and schedules for the installation of new electric meters have been drawn up and agreed, work has been organized to admit the teams of the contracting organization to the facilities. I hope that the coherence of actions will allow you to install all equipment within the deadlines set by the energy service contract and move to the stage of obtaining effect as quickly as possible. "