RSS
Логотип
Баннер в шапке 1
Баннер в шапке 2
Project

"The standard of LenSpecSMU" automated work with contractors in the environment of Pilot-ICE Enterprise

Customers: Etalon Group (Standard LenSpecSMU)

Product: Pilot-ICE (Industrial Civil Engineering)

Project date: 2018/04  - 2018/09

The Standard of LenSpecSMU company implemented a management system for the project organization and processes of information modeling of Pilot-ICE Enterprise and connected to it more than fifteen contractors. On November 2, 2018 the "ASCON Northwest Project Management" company which performed an implementation project reported about it.

Numerous construction contractors and the project organizations are involved in business processes Standard of LenSpecSMU. Before Pilot-ICE Enterprise implementation the operating procedure over the project was such: design engineers Standard of LenSpecSMU collected documentation from the contract project organizations, reported each sheet of a set to the approving experts, collected notes and sent them back to designers. The approved documentation kit was replicated in five paper copies and transferred to the construction organization to an object. Sometimes approving and designers began to communicate directly, passing the design engineer. As a result to collect a complete set, to follow relevance of documentation getting to it it was extremely difficult.

According to the results of implementation the template of structure of the project on which in Pilot-ICE each new project was created was created, connection of designers of contract organization directly to the Standard of LenSpecSMU database is organized. Designers install at themselves the client application of a system, are far off connected to the Standard of LenSpecSMU server, spread the project documentation and send it for approval to experts of the company. In case of notes contractors work them and update the document revision. After a statement the expert of LenSpecSMU presses the Sign button — the electronic signature, date and the facsimile approving are put automatically.

File:Aquote1.png
"We have two types of external contractors — the project organizations load files into a system independently, fill cards on each file, and general contractors and builders have an opportunity to browse documentation. For some work with Pilot-ICE Enterprise — additional loading, for others — a fast and convenient method to obtain up-to-date information. Together with ASCON the general training for all external partners was provided. Colleagues learned how to work in Pilot-ICE Enterprise and for what common goal it is necessary. It became obvious that thanks to a system interaction becomes simpler, the speed of approval of documentation significantly increases, the number of excess actions is reduced. In the near future the company is going to refuse paper almost completely. Construction contractors print that number of copies which is necessary on building".

Elena Udalova, chief of architectural and construction department Standard of LenSpecSMU
File:Aquote2.png

File:Aquote1.png
"The Pilot-ICE Enterprise system allowed to organize the centralized and structured archive of the project and work documentation on all projects "Standard of LenSpecSMU", to provide quick access of employees to the database and to adjust operational approval. Process of approval of documentation is implemented through issue of a task for approval, at the same time the designer issues it to employees Standard of LenSpecSMU as if they worked at one enterprise".

Natalya Zhuravina, technical lead of the project, "ASCON Northwest Project management"
File:Aquote2.png

For November, 2018 15 contractors are connected to Pilot-ICE Enterprise, and to each new partner with whom Standard of LenSpecSMU begins to cooperate, work in a system is necessary too. In all contracts which the company signs with the contractors developing the project documentation there is a point — documentation should be provided in Pilot-ICE Enterprise.