Customers: Expocenter Moscow; Advertising, PR and Marketing Contractors: Amdtekhnologiya Product: Complex projects of creation of the engineering systemsProject date: 2019/06 - 2019/12
|
2019: Integration of the additional hardware into the system of cold supply
On January 31, 2020 it became known that the engineering company of Amdtekhnologiya integrated the additional hardware into the system of cold supply of the central exhibition complex "Expocentre". Project implementation took six months. During this time system performance of cold supply was increased by 1.3 MW, reliability of the engineering systems is also increased.
to TsVK "Expocentre" there are more than 60 years in the market, the question of upgrade of the outdated systems of cold supply ripened long ago, and it is performed step by step, |
Works were carried out in the TsVK refrigerating center, providing with cooled water a complex conditioning system.
The additional chiller which allowed to provide reliable cold supply of a complex with the required load range was installed, reported Maxim Cuohan
|
According to him, the main complexity was connected with equipment installation in the refrigerating center and logistics. The installed dimensional equipment needed to be placed indoors where there were already refrigerators.
As a result of project implementation TsVK received necessary for it at this stage the modern energy efficient equipment, added the CEO of Amdtekhnologiya
|