The Softline company completed delivery of the software of Autodesk for ESM LLC company.

Prerequisites

ESM LLC (ECM, LLC) provides a full stroke of production of electrochemical machines of the ET series: from design and production before technology maintenance at customers and service maintenance; executes development of unique technology processes according to requirements of a number of high-tech industries of the industry.

Earlier, in design process, the company used platforms of different producers, it resulted in difficulties with data exchange between departments in the company. There were difficulties with obtaining qualitative design documentation in accordance with GOST. Besides, when converting files from one system in another the company very often faced data loss which led to high costs of temporary resources that, finally, led to finance costs. The decision on transition to the Autodesk platformAutoCAD Inventor Professional Suite was made", Timur Idrisov, the chief technologist of ESM LLC company noted.

Results

As a result of transition on new software, customer company increased the speed of preparation of design documentation, resolved issues of exchange and data, increased quality of projects.

Contract amount was more than one million rubles.

Customer

"Using functionality of the AutoCAD Inventor Professional Suite program engineers of the different directions of ESM LLC can work at the same time on the project, receiving qualitative results in short terms. It is important that the speed of release of projects was increased four times, all issues with exchange and data transmission which caused quality improvement of projects and, respectively, competitive advantage of the company in the market are resolved", – Timur Idrisov summarizes.