Datark modular data centers significantly reduced the launch of the IT infrastructure of the Atyashevsky IPC

Customers: Atyashevsky (Talina)

Contractors: Jet Infosystems
Product: Datark Optimod Complete Modular Data Center

Project date: 2025/01  - 2025/07

2025: Delivery of two modular data centers

The company DATARK delivered two modular DPC data processing centers (M) for IPC "," Atyashevsky which is part of the GC "." Talina Thanks to this, the company was able to launch the updated one as soon as IT infrastructure possible. The implementation of the project took less than six months, and the integration took place without stopping production processes. The integrator in the project was the center of network solutions "." Jet Infosystems Datark announced this on August 19, 2025.

The introduction of modular data centers has become part of the strategy for digital transformation and modernization of the IT services of the agricultural complex. Each of the World Data Centres is made in the format of a protected street module, resistant to external influences and suitable for year-round operation on open industrial sites. The infrastructure is designed to accommodate nine full-size telecommunications cabinets in each unit. At the same time, the total design capacity of one module exceeds 100 kW.

Both World Data Centre are based on DATARK OPTIMOD solutions and are equipped with freon precision air conditioners with built-in steam humidifiers. The solution architecture takes into account the requirements of energy efficiency, industrial safety and a high degree of availability. The total design capacity of the solutions allows you to support the operation of corporate ERP systems, digital production management platforms and security systems.

File:Aquote1.png
In the industrial environment, it is important not only to put a ready-made solution, but to accurately integrate it into the existing technological rhythm. We focused on real operating scenarios. Therefore, everything in the project - from architecture to cooling modes - was selected taking into account the specifics of the object and the requirements for process continuity, "said Mikhail Shumai, DATARK key customer manager.
File:Aquote2.png

According to Vsevolod Vorobyov, head of the data center of the Jet Infosystems network solutions center, one of the key tasks was to ensure high speed of operation and fault tolerance of the customer's systems.

File:Aquote1.png
The agro-industrial complex uses a set of interconnected production management systems, and every year the volume of information processed is growing. Together with the DATARK team, we created two identical data centers in different locations. Data center geodistribution ensures data redundancy, while fault-tolerant power supply and cold supply systems minimize the risks of production downtime. Thanks to the modular approach, we implemented the project from scratch in just a few months and can continue to replicate the solution, - said Vsevolod Vorobyov.
File:Aquote2.png