2025: Cancelling Construction

RusHydro refused to build the Mogokh small hydroelectric power station in Dagestan, explaining its decision by the economic inefficiency of the project. This was announced in November 2025 in the press service of the company. The company won the competition for the construction of a 49.8 MW station in 2021. For 15 years of payback, planned revenue was estimated at 20.3 billion rubles. at 2021 prices, but since then, economic parameters have changed significantly. Investments in construction were estimated at 13.6 billion rubles.[1]