Blagoveshchensky Reinforcement Plant (BAZ) (1C:Enterprise 8. TEID Equipment Repair and Maintenance Management)
Customers: Blagoveshchensky Reinforcement Plant (BAZ)
Contractors: Desnol Soft (Ithilium) Product: 1C:Enterprise 8. TEID Equipment Repair and Maintenance ManagementSecond product: TOIR 2 CORP mobile brigade Project date: 2020/06 - 2020/11
Number of licenses: 30
|
2020: Automation of M&R processes
In November 2020, the company Desnol Soft"" announced that Annunciation rebar plant was it had been selected as a pilot site for digitalizing the management of repairs and equipment maintenance at enterprises. OMK Groups The project lasted about 6 months. For two and a half months, the company "" Desnol Soft simultaneously conducted two stages of implementation, consultants examined, business processes TOiR adapted and configured the system "," 1C: TOIR 2 CORP conducted the integration of "1C: TOIR 2 KORP" with the system "," 1C: Plant Management in which accounting was carried out before implementation, and also taught users to work in a different format. And over the same period, Desnol Soft specialists debugged the system in production, connected it, mobile application "Mobile Brigade" which works in conjunction with a large system in online and offline modes. And all this remotely - during the period of quarantine as part of the epidemic COVID-19 , completely remotely.
According to the company, the scale of the project amounted to 18,998 repair objects. The objects of repair were steelmaking, forge press, foundry, hydraulic equipment, machines and furnaces, machines and mechanisms, pneumatic devices. 30 workplaces are automated.
The main factor that was taken into account when choosing a contractor (integrator) is the experience of implementing tools for automating repair management. Desnol Soft is the developer of the 1C: TOIR system and has experience in implementing more than 150 projects in the field of M&R automation, so the choice was made in favor of this integrator. said Vitaly Schukin, Director of Power Supply and Repairs of Blagoveshchensky Rebar Plant JSC |
Economic impact of implementation:
- Reduction of labor costs in M&R units: 15%
- 10% Reduction in Order Delivery Time
- Reduce hardware downtime by 10%
- 10% Faster Order Processing
To optimize the efficiency of work in 1C: TOIR, the mobile application "Mobile Brigade" was introduced as part of the project. Practice has shown: learning to work with a smartphone for linear workers is easier than mastering a computer. The mobile application works in conjunction with the "large" system 1C: TOIR 2 CORP and exchanges data with it. It is possible to work in online and offline modes. supplemented by Vitaly Schukin, Director of Power Supply and Repairs of Blagoveschensky reinforcing JSC "Plant" |