ICL completed the project of integration of 1C and Microsoft Dynamics AH on Kazancompressormash

Customers: Kazancompressormash

Kazan; Mechanical engineering and instrument making

Product: Microsoft Dynamics AX

Project date: 2007/12  - 2008/11

AF ICL-KPO company carried out in 2008 implementation of the integrated information management system on the Microsoft Dynamics AX platform to Kazancompressormash companies.

The complete solution covered all production cycle, from technology preparation of production before shipment of finished goods to customers. Now the stage of inspection of the enterprise and development of functional requirements to the ERP system is completed.

In December, 2014 ICL-KPO of AF completed the project of integration of 1C and Microsoft Dynamics AH at the kompressoro-construction enterprise JSC Kazancompressormash. Project implementation provided compliance of data in warehouse, production and accounting.

JSC Kazancompressormash keeps accounting in the customized configuration 1C of management of manufacturing plants, operational accounting, on terms and production schedules in Microsoft Dynamics AH. To create production costs in 1C on the basis of operational data of the ERP system, it was required to implement integration. On the basis of the detailed technical specifications developed by specialists of ICL-KPO of AF settings with step-by-step testing and transfer of results for the enterprise were carried out. Except support of compliance of data in warehouse, production and accounting, integration also allows to increase efficiency of information exchange, thanks to an exception of double entry of data.