RSS
Логотип
Баннер в шапке 1
Баннер в шапке 2
Project

The Krasnoyarsk hydroelectric power station completed external audit of IT infrastructure

Customers: Krasnoyarsk hydroelectric power station

Krasnoyarsk; Power

Contractors: NVision Group
Product: Projects of external audit of IT and security (in tch PCI DSS and SUIB)

Project date: 2011/02  - 2011/02

The NVision Siberia company integrator completed audit of IT infrastructure and information systems for JSC Krasnoyarsk Hydroelectric Power Station.

Implementation

During audit by specialists of NVision Siberia are inspected: server part, system of virtualization, directory service, backup system, data network, communication channels, legal security, perimeter systems, security system, engineering systems, electronic document management system and database systems of hydroelectric power station.

As a result the complex conclusion with the description of "narrow" places in a security system, fault tolerance and performance of the existing IT infrastructure, information systems of JSC Krasnoyarsk Hydroelectric Power Station and the recommendation about their elimination is submitted to the Customer.

Opinion

"Specialists of NVision Siberia showed the high level of understanding of features of functioning of IT systems and laid the foundation of effective strategy of IT development taking into account industry specifics of the power enterprise", - Iya Yudina, the head of information technology of JSC Krasnoyarsk Hydroelectric Power Station noted.