Customers: OGK-4 Contractors: InfoPro Group Product: InfoPro: Planning of the modesProject date: 2012/08
|
In August, 2012 the INFOPRO Group signed the agreement on implementation of automated information system on Surgut-2 Power Station, the largest thermal power station of Russia. Surgut-2 Power Station is a part of JSC E.ON Rossiya (OGK-4) along with such power plants as Beryozovskaya GRES, Shaturskaya GRES, the Smolensk state district power plant and Yayvinsky state district power plant.
The implemented system "INFOPRO: Planning of the modes" will carry out the following tasks at the station:
- calculation of technical and economic indicators of operation of the equipment;
- data of a steam-and-water, heat and electric balance (taking into account heat overflows) and distribution of fuel consumption between units;
- calculation actual and normative TEI according to normative models and methodical indications of the station, including tables of perezhogov/ekonomiya of fuel;
- logical control of reliability of the primary data obtained from the systems of the bottom level;
- carrying out calculations on the minimum period 15 minutes;
- formation and providing the corporate reporting on TEI.