Customers: RD Construction (RD Konstrakshn Management) Moscow; Construction and industry of construction materials Contractors: Mobile solutions for construction Product: StroycontrolProject date: 2016/10 - 2016/12
|
The project team from the customer | Integrator Consultant |
Prashchikin Sergey (Chief information officer (CIO))
|
не указана |
On February 21, 2017 it became known of an implementation project of a software package of Stroycontrol in RD Construction company. Integrator in the project "Mobile Solutions for Construction" company.
Project Results
Customer representatives, the general contractor and subcontractors – 65 users are connected to the program. Began to use a software package from the first days of the construction project.
Within the first month of use of software:
- about 1 thousand notes, a half of which is corrected, are created, and a third is checked and accepted;
- 1.5 thousand photos are loaded;
- more than 100 drawings are added for work.
We at last had a fast and convenient instrument of fixing of notes on quality of construction works. Earlier we had to accumulate notes. The multipage bulky document which weekly went to all subcontractors was as a result created. Now notes get to the necessary operators at once. At the same time control of execution is exercised 24/7. In the headquarters of construction on the big screen in the online mode there are new notes and also the course of correction of the current defects is displayed. Sergey Prashchikin, director of information technology of RD Construction |