"The southern Yakut electric networks" carried out hardware upgrade of control of power facilities

Customers: Southern Yakut electric networks

Aldan; Power

Contractors: RTSoft
Product: RTSoft: SMART KP2

Project date: 2016/09  - 2016/12

On February 14, 2017 the RTSoft company announced hardware upgrade of power facilities of JSC DRSK branch "Southern Yakut electric networks".

Project Results

Specialists of RTSoft in the IV quarter 2016 executed delivery, installation and autonomous equipment checkout on objects of RAO UES of the East:

  • PS-40 Enrichment factory
  • DP of the Neryungrinsky distribution zone.

In the dispatching office hall of "The southern Yakut electric networks", (2015)

The project on replacement of the equipment became pilot implementation of a product line of SMART KP2. Pilot implementation provided to the enterprises of JSC DRSK "Southern Yakut electric networks" technology updating and an economic benefit.

Feature of the project in partial upgrade of the operating system without stopping works of substations. Specialists of RTSoft in parallel installed own equipment, having established synchronous cooperation between old and new controllers.

During the project own technological solution is developed for ensuring end-to-end passing of signals from the old equipment on the top level. All data from substations continued to be fixed and displayed without loss.

Except supply of equipment of telemechanics, its autonomous adjustment and complex check of passing and display of signals, the unrolled scheme of Neryungrinsky district of the electric networks on a board of the manager is created. Integration of the equipment is executed on 12 substations located on mutual removal up to 150 km.