Far Eastern Distribution Network Company
Since 2005
Russia
Far Eastern Federal District of the Russian Federation
Blagoveshchensk
Shevchenko St., 28
Content |
Assets | Owners |
+ IDGC of the Far East |
Information technologies in Rosseti
Main questionnaire: Information technologies in Rosseti
History of development of the company
According to Article 6 of the Federal Law "About Features of Functioning of Power Industry during a Transient Period and about Making Changes in Some Legal Acts of the Russian Federation …." of 3/26/2003 No. 36-FZ combination of activities for transfer of electrical energy and to supervisory control in power industry with activities for production and purchase and sale of the electric power is forbidden to legal entities. According to the Board of Directors of JSC RAO UES of Russia given by the requirement on September 2, 2005 (protocol No. 202) the decision "About the Project of Reforming of the Power Companies of the Far East" the providing creation of JSC Far Eastern Distribution Network Company based on distribution network assets of JSC Amurenergo, JSC Dalenergo, JSC Khabarovskenergo, JSC Southern Yakutskenergo with which only shareholder after completion of reforming of the power companies of the Far East was made JSC Far Eastern Energy Company will be.
On December 22, 2005 state registration of "Far Eastern Distribution Network Company" Open joint stock company is performed.
After cession of property of JSC Amurenergo, JSC Dalenergo, JSC Khabarovskenergo, JSC Southern Yakutskenergo in authorized capital of JSC DRSK (12/31/2006) since 1/1/2007 JSC DRSK begins operating activities and performs transportation of electrical energy through distribution networks in the territory of the Amur region, Khabarovsk Krai, the Jewish Autonomous Region, Primorsky Krai, the Southern Region of Sakha (Yakutia) Republic.
The main objective of reforming of the power companies of the Far East was creation of the companies specializing in separate types of activity: sale is JSC Far Eastern Energy Company, generation - JSC Far Eastern Generating Company, transfer of electrical energy - JSC Far Eastern Distribution Network Company.
According to the solution of Board of Directors of JSC RAO UES of Russia of 9/2/2005 No. 202 on question 2. "About the project of reforming of the power companies of the Far East" decided:
- 2.1. Approve the project of reforming (the scheme of reforming) of power supply systems of the Far East providing:
- 2.1.1. Creation of JSC Far Eastern Generating Company based on the generating and heatnetwork assets of JSC Dalenergo, JSC Khabarovskenergo, JSC Amurenergo, LUTEK Ltd and JSC Yakutskenergo (Youzhny energorayon) which only shareholder after completion of reforming of the power companies of the Far East will be JSC Far Eastern Energy Company;
- 2.1.2. Creation of JSC Far Eastern Distribution Network Company based on distribution network assets of JSC Dalenergo, JSC Khabarovskenergo, JSC Amurenergo, and JSC Yakutskenergo (Youzhny energorayon) which only shareholder after completion of reforming of the power companies of the Far East will be JSC Far Eastern Energy Company;
- 2.1.3. Isolation of objects of ENES belonging to JSC Dalenergo, JSC Khabarovskenergo, JSC Amurenergo, JSC Yakutskenergo (relating to the Southern energorayon) by creation of 100% of DZO of the specified companies with entering into authorized capital of objects of ENES and further accession of the created companies to JSC Mednogorsk Copper-Sulphur Plant Centre;
- 2.1.4. Creation of the uniform Holding company is JSC Far Eastern Energy Company based on assets of JSC Dalenergo, JSC Khabarovskenergo, JSC Amurenergo, JSC Yakutskenergo and LUTEK Ltd;
- 2.1.5. Preserving in JSC Far Eastern Energy Company of functions of sale of the electric power;
- 2.1.6. Preserving of function of sale of energy at JSC Yakutskenergo in the territory of the Southern energorayon of the Sakha (Yakutia) Republic to the solution of a question of cross subsidizing in the Sakha (Yakutia) Republic.
- 2.2. Approve the list of the actions (performed in parallel) for project implementation of reforming of power supply systems of the Far East:
- 2.2.1. JSC Yakutskenergo organization of 100% of DZO - JSC Southern Yakutskenergo with authorized capital payment property of the Southern power zone of JSC Yakutskenergo;
- 2.2.2. Creation of JSC Far Eastern Energy Company by reorganization of JSC Khabarovskenergo, LUTEK Ltd, JSC Amurenergo, JSC Southern Yakutskenergo and JSC Dalenergo in the form of merge;
- 2.2.3. Organization one of specified in item 2.2. AO-energo of 100% of DZO: JSC Far Eastern Generating Company with the following provisions:
- authorized capital of JSC Far Eastern Generating Company of 5,000,000 (five million) rubles;
- category, type, nominal value, the number of the shares placed at organization: personalized ordinary shares (one) kopek with a nominal value of 1 for an action in number of 500,000,000 (five hundred million) pieces;
- list of Founders and share of their participation in authorized capital of JSC Far Eastern Generating Company: AO-energo – 500,000,000 (five hundred million) ordinary registered shares (100% of authorized capital of JSC Far Eastern Generating Company);
- order (term) of payment of actions: within 1 month from the moment of state registration of JSC Far Eastern Generating Company;
- payment method of actions: in cash.
- 2.2.4. Organization one of specified in item 2.2. AO-energo of 100% of DZO: JSC Far Eastern Distribution Network Company with the following provisions
- authorized capital of JSC Far Eastern Distribution Network Company of 5,000,000 (five million) rubles;
- category, type, nominal value, the number of the shares placed at organization: personalized ordinary shares (one) kopek with a nominal value of 1 for an action in number of 500,000,000 (five hundred million) pieces;
- list of Founders and share of their participation in authorized capital of JSC Far Eastern Distribution Network Company: AO-energo – 500,000,000 (five hundred million) ordinary registered shares (100% of authorized capital of JSC Far Eastern Distribution Network Company);
- order (term) of payment of actions: within 1 month from the date of state registration of JSC Far Eastern Distribution Network Company;
- payment method of actions: in cash.
- 2.2.5. Increase in authorized capital of JSC Far Eastern Generating Company by placement of additional stocks with their payment in the generating and heatnetwork assets of JSC Dalenergo, JSC Khabarovskenergo, JSC Amurenergo, LUTEK Ltd and JSC Southern Yakutskenergo;
- 2.2.6. Increase in authorized capital of JSC Far Eastern Distribution Network Company by placement of additional stocks with their payment in distribution network assets of JSC Dalenergo, JSC Khabarovskenergo, JSC Amurenergo and JSC Southern Yakutskenergo;
Core activities of Society:
- rendering services in transfer of electrical energy;
- rendering services in distribution of electrical energy;
- supervisory control and observance of the modes of energy saving and energy consumption;
- rendering services in accession to the electric networks;
- rendering services in collecting, transfer and processing of technology information, including data of measurements and accounting;
- control of safe service of electrical units at the consumers connected to the electric networks of society;
- activities for operation of the electric networks;
- project and estimate, survey, research and design works;
- rendering forwarding services;
- execution of works, defining conditions of parallel operation according to the modes of the Power pool system of Russia within contractual relations;
- operation under agreements with owners of the power objects which are not on balance of Society;
- ensuring working capacity and operability of a utilities equipment according to the existing regulatory requirements, maintenance, diagnostics, repair of the electric networks and other objects of power grid economy and also technology management of them;
- ensuring working capacity and operability, maintenance, diagnostics and repair of networks of technology communication, measuring instruments and accounting, the equipment of relay protection and antiabnormal automatic equipment and other, technology equipment connected with functioning of power grid economy and also technology management of them;
- development of long-term forecasts, perspective and current plans of development of an electric grid, target comprehensive scientific and technical, economic and social programs;
- development of the electric networks and other objects of power grid economy including design, engineering researches, construction, reconstruction, modernization, installation and adjustment;
- development of networks of technology communication, measuring instruments and accounting, the equipment of relay protection and antiabnormal automatic equipment and other technology equipment connected with functioning of power grid economy including design, engineering researches, construction, reconstruction, modernization, installation and adjustment, etc.
Structure of the company and branches
The following branches and representations are a part of Society:
- Amur electric networks
- Seaside electric networks
- Khabarovsk electric networks
- Electric networks of the Jewish Autonomous Region
- Southern Yakut electric networks
- Representative office of JSC DRSK Moscow
The number of branches of the electric networks – 5.
Total length of the networks which are under authority of JSC DRSK is 52,997 km.
Total quantity of the serviced power substations - 699.