Project

Jet Infosystems constructed container DPC for ABI Product

Customers: ABI Product (ABBYY Product)

Vladimir; Food industry

Contractors: Jet Infosystems, Datark
Product: DPC Projects of creation and upgrade

Project date: 2018/09  - 2019/01

2019

On January 31, 2019 ABI PRODUCT announced commissioning container data center. The project is executed IT- integrator "Jet Infosystems".

According to the company, creation of own container DPC is caused by growth of the company and the product demand, and respectively, need of increase in IT capacities and implementations of the accompanying services.

File:Aquote1.png
This project – an important stage of development of production capacities of ABI PRODUCT. Constantly growing demand for products of the company is the main factor of upgrade of the current business processes, formations of technologies with the maximum extent of automation and adaptation under individual requirements of the enterprise. We invest in IT as we understand that modern technologies are capable to create competitive advantage for business.

Nail Aribzhanov, technical director of ABI PRODUCT
File:Aquote2.png

Use of the non-standard container increased on width and height and also special power connectors of the increased power became feature of the project. This solution — development of Marechal Electric Group company which was for the first time sold by experts of the system integrator in the Russian market specified in Jet Infosystems.

Project implementation took place in several stages. The data center was brought together by partners of integrator in Yekaterinburg. After end of a test stage, KTsOD it was transported for installation on the platform selected by the customer. It is important that the command Jet Infosystems acted in this project not only as classical IT integrator, but also as the collaborator of installation and construction works on preparation of the platform for data center, including a base tab.

KTsOD is equipped the systems of regular power supply, conditioning, gas fire extinguishing, access control, video surveillance. For ensuring fault tolerance the most part of subsystems has reservation of not less "N+1". On a case of interruptions in the electric power automatic translation of DPC on power supply from DGU expected 8-hour work without refueling is provided. Modular construction of data center reliably protects the equipment placed in it from electric, temperature, climatic and shock loads. Operating range of temperatures of DPC is from -40 °C to +40 °C.