Data Center DataLine NORD-4 Moscow Korovinskoye Shosse, 41

Product
Developers: DataLine (Data Line)
Last Release Date: 2020/03/24
Technology: DPC

Content

NORD-4 - data center, an asset of the company DataLine. Сертификаты Tier III Certified: Constructed Facility, Tier III Certified: Design, ISO/IEC 27001:2013. Located NORD 4 in SAO at the address: Moscow, m. River station Korovinskoye Shosse, 41. 2016 racks. Area - 11700 sq.m. Power - 20,000 kVA

2020: Passing the Uptime Institute recertification

On March 24, 2020, DataLine announced that its NORD-4 data center had been re-certified by the Uptime Institute, confirming compliance with Tier III: Certification of Operational Sustainability, Silver. Uptime Institute Tier III: Operational Sustainability certification is a key standard for evaluating data center management and operation performance. The successful completion of the audit confirms that the data center has built all the necessary operation processes and a qualified team is working at the site.

Passing Uptime Institute Recertification
File:Aquote1.png
Successful certification confirms the compliance of the data center with world practices in terms of operational stability. Thanks to this, we can guarantee our customers high availability of IT resources and services operating on the basis of the NORD-4 data center,
commented by technical director Sergey Mishchuk
File:Aquote2.png

As of March 2020, the NORD-4 data center has the entire Tier III level Uptime Institute certification set: Design, Constructed Facility, Operational Sustainability.

The NORD-4 data center is located in the north of Moscow, on Korovinsky highway, 41. The capacity of the data center is 20,000 kVA, 8 halls are designed for 2016 racks.

2018

ISO/IEC 27001:2013 Certification

The company passed the next audit for compliance with the requirements of the international standard ISO/IEC 27001:2013. Certification was carried out at two sites - OST and NORD. The audit was conducted by BSI.

During the annual inspection, the DataLine confirmed that the company's Information Security Management System (SMIB) meets the requirements of ISO/IEC 27001:2013. The following services were audited:

Tier III Certification: Operational Sustainability

The first stage of the NORD-4 data center passed the certification of operation processes for compliance with the Uptime Institute Tier III: Operational Sustainability standard. Previously, the data center was certified according to Tier III: Design and Constructed Facility standards.

As part of the certification, the failure-free operation of the data center is checked in three categories: operation, construction characteristics and location of the facility. Management decisions regarding the number and training of personnel, as well as the operations and maintenance processes of the data center are evaluated.

Audit of the first stage of data center of NORD-4 was booked by experts of Uptime Institute. Inspections took place over three days - from October 10 to 12, 2017, as a result of which the module received a Tier III: Operational Sustainability, Silver level.

The certificate confirms that the module meets the following criteria:

  • failure-free operation of infrastructure,
  • configured management and operation processes,
  • compliance with building design requirements,
  • low production risks on site.

The received certificate is valid for two years from the moment of receipt.

Construction of cooling system

The companies AMDtehnologiya"" DataLine and in January 2018 announced the completion of the 4th, final stage of construction and engineering equipment DPC NORD-4 on Korovinsky highway in. As To Moscow a result of the project, a modern cooling system was built, the total cooling capacity of which is 10.5 mW. More. here

2017

Commissioning of the last power center

The company DataLine on December 27, 2017 announced the commissioning of the last NORD-4 energy center. The data center is now fully launched. According to the end of 2017, its installed capacity is 20 thousand kVA, the number of stalls is 2016, and the total volume of data centers DataLine is 4711 racks.

The first NORD-4 halls were launched in February 2015. The data center is designed and built in accordance with TIER III Uptime Institute standards. In June 2015, DataLine received a project certificate (Design), and in March 2016 she certified the finished project (Facility). At the end of 2017, Operational Sustainability certification of the first NORD-4 power module took place.

The NORD-4 data center also houses backup offices for the company's customers: open space, dedicated jobs, meeting rooms and a dining room. Engineering communications, telephony and the Internet were carried out in the office wing, the room has a separate entrance from the reception. NORD-4 halls already have several large customers. Installing client hardware.

File:Aquote1.png
NORD-4 is our largest and most ambitious project. In it, we realized the accumulated experience in the design, construction and operation of data centers, "said DataLine Director General Yuri Samoilov. - The launch of the last energy center is the main result of 2017 for the company.
File:Aquote2.png

NORD-4 Data Center Phase 3

In the spring of 2017, DataLine commissioned two new halls in NORD-4 with a design capacity of 504 stalls. With this launch, the company increased the volume of its network of commercial data centers to 4207 racks.

"The phased
commissioning of NORD-4 capacities helps us to quickly scale our network of data centers, and the project with independent energy centers allows us to build new queues without interfering with already operating machine halls," said DataLine Director General Yuri Samoilov. "By the end of the year, the fourth stage of 504 racks will be launched."

2016: NORD 4 DataLine Data Center certified by Uptime Institute Tier III Constructed Facility

The data center DataLine NORD 4, previously certified by the Uptime Institute Tier III: Design, in early 2016 passed the certification of the finished object for compliance with the design solution Uptime Institute Tier III: Constructed Facility.

As part of the Uptime Institute Tier III: Constructed Facility certification, the as-built documentation and equipment of the main NORD 4 engineering systems (power, cold supply and fuel supply) were checked, as well as testing of data center engineering systems for compliance with backup requirements.

During the tests of the engineering systems of the data center, more than 30 tests were carried out. At the first stage, the correct operation of the systems was checked when switching from the city power supply to diesel generators and vice versa. During subsequent inspections, critical infrastructure elements were alternately excluded from work: DGP, chillers, air conditioners, pipeline sections. During the tests, heat guns were installed in the machine rooms with operating client equipment to ensure full load on the power and heat supply systems provided by the project. Uninterrupted fuel supply from the storage to DGP tanks was checked both in automatic and manual modes.

In general, the 4-day test program was completed in 3 days.

2015

Second Data Center Queue

On December 14, 2015, DataLine announced the commissioning of the second stage of the NORD 4 data center.

The total number of racks in the data center network increased to 3.7 thousand, which made it possible to achieve a total installed capacity of 38.2 thousand kVA. The design capacity of the Romeo and Sierra halls is 500 posts, the area is 1000 m ².

According to the company's statement, as of December 14, 2015, four NORD 4 machine halls (per 1 thousand stalls) out of eight operate in normal operation. The third and fourth modules are expected to be launched in 2016 - 2017.

File:Aquote1.png
author = Yuri Samoilov, CEO DataLine
NORD 4 is the result of the accumulated experience of DataLine in the design, construction and operation of data centers: in it we implemented our most successful solutions, complementing them with the expertise of the Uptime Institute and the best world practices. It is nice to realize that it was our team that was able to implement such a large-scale project, and, of course, the launch of the second stage of the data center is a wonderful New Year's gift for the company and customers.
File:Aquote2.png


Two rooms of NORD 4 data center put into operation

On March 2, 2015, DataLine announced the commissioning of the first two halls on the 504 rack of the NORD 4 data center.

On February 25, 2015, installation of customer equipment began in the Victor and Whiskey halls.

NORD Data Center, 2014


NORD 4 engineering infrastructure as of March 2, 2015

  • 4 power centers (44 UPS, 16 DGP);

  • total installed capacity - 20,000 kVA;

  • own fuel storage with volume of 100 m3.

In the new data center, as in the data center OST 1, a chiller cooling system is installed.

The NORD 4 data center is designed and built in accordance with TIER III Uptime Institute standards. As of March 2, 2013, an official conclusion on certification of the project has not been received. The plans DataLine certification of the finished facility, operation processes, commissioning of the 2nd stage of halls on 504 racks.

"In NORD 4, we implemented all the best solutions accumulated for our practice of designing and building our own data centers," said Yuri Samoilov, CEO of DataLine. "It is significant that the most experienced team in the market will operate such a large-scale data center."

According to the company's plans, 8 machine halls for 2016 racks will be commissioned in the data center. The total area of ​ ​ the data center will be 11.7 thousand m2.

2013-2014

Data Center Expansion

On April 18, 2013, DataLine announced plans to expand the NORD data center on Korovinsky Highway: the company began construction of a new NORD 4 data center, designed for 2,000 racks. DataLine CEO Yuri Samoilov told TAdviser that in 2014 DataLine will launch the first halls.

According to Samoilov, the new data center will consist of eight halls designed to accommodate up to 250 racks with equipment in each. The company expects to launch the first stage of the data center by the summer of 2014, said TAdviser CEO DataLine.

2010-2012

INLINE Technologies announced in September 2010 the completion of a project to create a network infrastructure for the second commercial data center (DPC) of DataLine, also part of the ITG holding (INLINE Technologies Group).

The network infrastructure is built on Juniper Networks equipment.

The creation of the data center infrastructure located on 41 Korovinskoye Highway is the second project carried out by INLINE Technologies for the company DataLine. The first - the construction of information and communication infrastructure - INLINE Technologies implemented for the data center on the street. Borovaya, 7.

The network infrastructure of the data center at Korovinsky is based on a two-level hierarchical topology.

The upper layer of the network hierarchy - the core module - is formed by a pair of Juniper MX480 mutually redundant modular routers. Their connection to the trunk is made through two points - one line provides a connection to the MMTC-9 node, the other - directly to the node in the data center on Borovaya. For fault tolerance, these lines are terminated on different MX480 routers.

The lower layer of the hierarchy is the access module, which is formed by a stack of Juniper switches of the EX4200 series, operating using virtual chassis technology - all switches are combined into a single logical device. The fault tolerance of connecting the virtual EX4200 chassis to kernel routers is achieved by duplicating connections.

The data center at Korovinsky is connected to the MPLS-network of the DataLine company, created on Cisco equipment. Thus, the integration of Cisco and Juniper technologies and solutions allows us to talk about the construction of a multivendor network infrastructure in DataLine.

The official opening of the second data center of the Data DataLine company (41 Moscow Korovinskoye sh.) Took place at the end of June 2010.

  • The area of ​ ​ the technological hall of the commercial data center (DPC) is 830 square meters. m (3 halls) (Borovaya, 7)

On August 1, 2012, DataLine began construction of a building for two new data center halls on Korovinsky Highway. The new three-story building will house two halls with a total area of ​ ​ 1460 m2 for 400 commercial racks with an average capacity of 6 kVA. The total installed capacity will be 4000 kVA. The delivery of the facility is scheduled for the first quarter of 2013.

The company DataLine, part of the holding ITG (INLINE Technologies Group), announced in September 2012 the opening of a second building on 405 commercial racks with an area of ​ ​ 1879 m2 on the territory of the Korovinskoye data center in northern Moscow. The entire range of cloud services will be provided at this facility along with classic computing and telecommunications services.

The company's network of data centers includes a data center on ul. Borovaya (OST) with 583 racks and a data center on Korovinsky highway (NORD) with 1208 racks. Both objects are connected to each other by a fiber-optic communication line (VHF) with a capacity of 40 Gbit/s. The total bandwidth of communication channels is 150 Gb/s, the total bandwidth in the Internet is up to 50 Gb/s. NORD and OST data centers have presence points on MMTS9 and MMTS10, participate in traffic exchange points MSK-IX and DATA-IX. Network infrastructure (equipment, cable routes) is reserved according to the 2N principle.

The DataLine has about 300 customers. Most of the services in the service structure are still occupied by the collocation service, but the share of cloud services is gradually increasing.

According to the growth rate of consumption of services, collocation is occupied by social networks. In second place is the financial sector. At the same time, the average number of racks per customer in the financial sector is 8, while in the remaining sectors there is an average of 4.1 racks per customer.

In 2011, four new machine rooms (585 racks) were put into operation and two new sites are planned to be built in the next year. In accordance with the company's prospective development plans, by 2014, upon completion of the construction of the fourth building on the territory of the Korovinskoye data center, the total number of racks in the data centers of the DataLine will reach 3857, the area of ​ ​ the data center - 11 111 m2, and the total installed capacity - 44.6 mW. The company's revenue is expected to grow by 2.7 times from 2012 to 2014.