The cost of building the airport increased to 28 billion rubles
In mid-July 2024, it became known that the construction of the new Arkhyz airport complex began in the Karachay-Cherkess Republic. The total cost of construction is about ₽28 billion, and the completion of the work is scheduled for 2028.
According to RIA Novosti, the concession agreement on the construction of the airport was signed within the framework of the Caucasian Investment Forum by the head of the KCR Rashid Temrezov and the general director of the Airports of the Regions Management Company Yevgeny Chudnovsky. Under the terms of the agreement, a terminal, a runway with taxiways, an apron, lighting equipment and other aerodrome infrastructure will be built within the framework of the project.
The regional government will additionally finance the design and construction of external communications for the airport and build an access road, and air navigation facilities will be created at the expense of the federal budget. The head of the republic expressed confidence that this strategically important agreement will go down in the history of Karachay-Cherkessia as the start of the largest investment project, which will have a multiplier effect for the entire economy of the region and will become a key factor in the development of the tourism cluster.
Therefore, this is a very important project for us not only in the development of transport infrastructure, but also in the socio-economic development of the republic, "he said. |
According to the Deputy Prime Minister of RFAlexander Novak, by 2030 it is expected that the tourist flow in the region will reach 3 million people. Novak noted that the construction of its own airport will be an important factor in the development of the entire tourist cluster of the republic, an increase in the mobility of local residents, and will also have a positive impact on the economy as a whole - this is an increase in passenger traffic, and the construction of new infrastructure, and the creation of new jobs, and the development of production.[1]
Start of airport construction
On April 23, 2024, information appeared that the Airports of the Regions holding was starting the construction of the first airport in the Karachay-Cherkess Republic (KCR). The implementation of the project will cost approximately 25 billion rubles.
As of 2024, Karachay-Cherkessia is the only region of the North Caucasus where there is no air harbor of its own. Meanwhile, the appearance of such an object is expected to increase the number of tourists in the region by about half by 2030. The head of the KCR Rashid Temrezov announced plans to build an airport at the end of 2023. As potential investors in the government, structures close to Roman Trotsenko, Oleg Deripaska, the former governor of the Krasnodar Territory, Alexander Tkachev, were discussed.
They plan to build an air harbor near the village of Zelenchukskaya. The airport is expected to be international, with a 3.2 km runway. Pre-project proposals for the construction of the facility, as noted by Kommersant the newspaper "," by order of JSC UK "Airports of the Regions" was carried out by FSUE GPI and NII GA "Aeroproekt." Construction the airport, it is argued, should not have a negative impact "on objects, the AEROSPACE FORCES Ministry of Defense of Russia optical telescope of the SAO RAS and the Ratan-600 radio telescope," which are located in the immediate vicinity of the site for the future complex.
RBC reports that airports in the regions of the North Caucasus district are experiencing increased loads and record traffic growth amid the closure of 11 airports in the south and central Russia part from 2022. At the same time, some experts say that it will be possible to recoup the project of a new air harbor in the KCR only if countries Europe remain closed by 2030.[2]