| Customers: Linx (MPA Communication) formerly Linxdatacenter Moscow; Information Technology Contractors: DataDome Product: Integrated IT Infrastructure ProjectsProject date: 2025/02 - 2025/05
|
2025: Reconstruction of engineering systems in the Moscow data center
DataDome on June 11, 2025 announced the completion of the reconstruction of the complex of engineering systems at the Linx Datacenter data center in Moscow, Linx Datacenter. As part of the project, additional server racks with a total capacity of 133 kW were designed and installed. The project was implemented without disconnecting the existing equipment.
The project was turnkey, including design, supply, construction, installation and commissioning. An important condition was the work in the data center without disconnecting the existing equipment. This required the company to pay special attention to the uninterrupted operation of the power supply and air conditioning systems.
As part of the project, the integrator presented technical solutions for installing 19 additional server racks in the machine room with an average consumption of 7 kW.
The company also developed documentation for air conditioning, power supply, architectural solutions, automatic fire alarm, video surveillance systems and dispatching, access control and control systems.
During the construction and installation works, construction preparation of the premises was carried out, the main distribution board and uninterruptible power supply systems, automatic fire alarm, video surveillance and dispatching, access control and control were modernized. The modernization project also included the supply and installation of IBPDelta Electronics with a total capacity of 300 kW and Envicool in-row air conditioners with a total capacity of 200 kW.
DataDome managed to implement the project in a short time - the entire process, from the moment the contract was signed and the design began to be installed in the installed racks of the Linx Datacenter data center, took three months.
{{quote 'We are proud to be able to quickly complete this project with all Linx requirements in mind. The work of our team was organized in such a way as to prevent failures of the existing IT infrastructure of the company. The engineering solutions that we implemented not only increased the capacity and capacity of the data center, but also strengthened its status as a reliable data center. We are confident that this modernization will contribute to the further development and stable operation of the Linx Datacenter data center, "said Andrey Pavlov, CEO of Datedom. }}
| Linx continuously develops its services and modernizes its infrastructure to provide customers with a reliable modern IT platform for their growing business challenges. DataDome completed the work in a short time, and the quality of the work and the approach to the implementation of the project fully met our expectations, "said Linx CEO Mikhail Vetrov. |