2025: Launch of a new power unit for 30 billion rubles

Siberian Generating Company commissioned power unit No. 2 at the Krasnoyarsk TETs-3. He began supplying electricity to the unified energy system of Russia. This was reported in December 2025 in SGK. The company began implementing the project for the construction of power unit No. 2 in 2022. Investments exceeded 30 billion rubles. The new power unit will provide an additional 185 MW of electrical power. The total potential of one of the country's most advanced solid fuel thermal power plants is now 393[1]network