DPC SafeData Udomlya

Product
Developers: SafeData - Data Storage Center, Rostelecom - Data Centers (Rostelecom-Data Center, RTK-Data Center)
Date of the premiere of the system: 2018/09/06
Last Release Date: 2022/02/15
Technology: DPC

Content

Main article: Data center (data center)

2022: Launch of an additional four halls at the 800 of 40 MW racks

Rostelecom-Data Center Group of Companies on February 15, 2022 announced the launch of the second stage of Udomlya MegaData Center. Additional capacities at the site in the Tver region are already available to customers.

The second stage of the data center is four halls with 800 racks with a total capacity of 8 MW. Specifically for this project, Rostelecom-Data Center built a fiber-optic path to ensure the best network connectivity. Thanks to this network architecture, customers can create geographically distributed solutions on several sites, for example, with the participation of data centers of the company in Moscow and St. Petersburg, as well as use the services of other data centers without additional difficulties.

Customers of the data center will have access to a single set of services presented at all sites of the Rostelecom-Data Center geo-distributed network: hosting server equipment (colocation), cloud infrastructure (Infrastructure-as-a-Service, IaaS) and services, telecom services, backup and DR1, information security services and many others.

File:Aquote1.png
The high demand for the capacity of our site in Udomla confirms that customers appreciated all the growth opportunities at the computing capacity at Udomla MegaDO, although they were initially restrained in relation to the site remote from Moscow. The first stage is fully filled, 50% of the second is also reserved by customers, "said Yuri Samoilov, First Deputy General Director of Rostelecom-Data Center, General Director of DataLine. The project involves expanding to five queues with a total capacity of 4,000 racks. The construction of the third module with 800 racks will be launched after the implementation of all the capacities of the current queue.
File:Aquote2.png

2019: Rostelecom put Udoml data center into industrial operation

Rostelecom-Data Center (a subsidiary of Rostelecom) put into commercial operation in July 2019 the Udoml data processing center (DPC), located near the Kalinin NPP in the Tver Region.

The construction of the data center at the Kalinin NPP site is a joint project of Rostelecom and Rosenergoatom. In accordance with the agreement, Rosenergoatom built and leased the building to Rostelecom for a period of 30 years. The operator was engaged in designing and creating engineering infrastructure in accordance with his own requirements for reliability and stability of the data center.

The design capacity of the Udomlya data center is 4 thousand rack seats, currently modules with a total capacity of 800 rack seats are ready for the placement of customer equipment. In the commissioned data center, the placement of client equipment has already begun.

File:Aquote1.png
"Udomlya Data Center is the largest project in our strategy to create a national geodistributed network of data centers. The partnership with Rosenergoatom made it possible to create a unique facility in terms of security, scale, and electricity tariffs. The demand for cloud services is growing rapidly: Rostelecom's revenue from data center services is increasing by 30% year-on-year. The largest data center in Russia will meet the rapidly growing demand of state and corporate customers on attractive market conditions. We offer a full-fledged cloud service: the supplier creates and operates the computing infrastructure on its own, providing the client with a ready-made solution with a guaranteed level of quality, "said Pavel Kaplunov, vice president of cloud services at Rostelecom, general director of Rostelecom-Data Center.
File:Aquote2.png

The Rostelecom data center at the Kalinin NPP site is the largest project in Russia and one of the largest in Europe. The first stage is three buildings for housing equipment and an administrative-office building, the supplied capacity is 48 MW. The area of ​ ​ each building is almost 11.5 thousand square meters.

The total design capacity of the first stage of the data center in Udomla is 4.8 thousand, of which 4 thousand racks will be located in the Udoml data center of the Rostelecom group, and 800 resistant seats in the Kalininsky data center of the Rosenergoatom concern.

2018: Completion of design documentation

On September 6, 2018, the company DataDome announced the completion developments of design documentation for the operator DPC SafeData , a subsidiary of "." Rostelecom Data Center will appear in the city of Udomlya. Tver region The work begun in October 2017 was completed in May 2018.

Expanding high-tech applications requires consolidation of computing resources and information storage, which significantly reduces the cost of maintaining networks. This is especially important for large corporations, including Rostelecom, the DataDome noted.

Data center specifications developed for SafeData:

  • DPC installed power - 8 MVA;
  • DPC area - 6000 m2.
  • number of server racks - 820;
  • planned consolidated data center rating - Tier III;
  • uninterruptible power supply system - 6 DIBP with capacity of 2000 kVA each;
  • cooling system - 5 chillers of 1094 kW and 48 precision cabinet air conditioners of 102 kW each.