Rosseti Ural (public name of OJSC Interregional Distribution Grid Company of the Urals, IDGC of Urals) transmits electricity via 110 kV - 0.4 kV electric networks and technological connection of consumers to electric networks.
Aktivs
As of December 2019, Rosseti Ural includes three branches - SverdlovEnergo, Chelyabenergo and Permenergo, as well as a subsidiary - Yekaterinburg Electric Grid Company JSC.
Information Technology in Rosseti
Main questionnaire: Information technology in Russia
History
2025
Placement of third-party container data centers at their substations
On December 11, 2025, a meeting of the Sverdlovsk Union of Industrialists and Entrepreneurs in Yekaterinburg took place. In this event, Rosseti Ural spoke about the deployment of third-party container data centers (DPCs) at its substations.
According to the deputy director of Rosseti Ural for technological connection and development of additional services Yuri Chernikov, the company has a ready-made infrastructure at its substations to reduce the capital costs of the business for the construction of a data center. Sverdlovsk 110/10 kV substations Ferrosplav and Chekmash were cited as examples. Chernikov noted a shortage of capacities for data centers in cities with a population of one million. Therefore, in his opinion, it is necessary to create a new infrastructure.
Denis Tarasov, director of the separate division of RTK-Data Center (a legal entity of Data Storage Center JSC, part of the Rostelecom group), emphasized the importance of placing data centers near consumers to ensure free access for personnel. He pointed to the problem of the lack of free land near substations with free capacity.
The head of the Rosseti group, Andrei Ryumin, announced the need to expand generating capacities and network construction due to the increase in energy consumption of the data center. According to him, the supply of electricity to data processing centers on the territory of Rosseti's work exceeds 1 GW, and the volume of signed contracts is another 1.5 GW.
According to the Unified Energy System (UES) of Russia, as of April 2024, the actual attached capacity of the data center was estimated at 2576 MW. According to the calculations of CHINT, by 2035 Russia will need at least 5 GW of additional capacity for this industry. Modern engineering solutions, according to the Chief Marketing Officer of CHINT, reduce data center power consumption by 30%, which is equivalent to saving more than 1 GW.[1][2]
Purchase of Chelyabinsk energy sales company "ATEK74"
Rosseti Ural bought 100% of the ATEK74 energy sales company operating in Chelyabinsk. This became known in January 2025. Read more here
2024: Appointment of Vladimir Ryabushev as CEO of PJSC Rosseti Ural
In September 2024, PJSC Rosseti Ural replaced the general director: Vladimir Ryabushev was appointed instead of Alexander Pyatigora. This is evidenced by the data of the service "Kontur. Focus." Read more here.
2019
As of December 2019, Rosseti Ural has more than 150 thousand km of cable and overhead power lines, 36.3 thousand substations with a total installed capacity of more than 52 thousand. MBA.
2011
As of March 2011, more than 1.6 million consumers were connected to the electric networks of IDGC of the Urals, including 30 thousand of the largest industrial enterprises in the Ural region. The company manages distribution network companies in 4 regions.
Notes
| | The site content is translated by machine translation software powered by PROMT. The machine-translated articles are not always perfect and may contain errors in vocabulary, syntax or grammar. Read original article If you find inaccuracies or errors in the results of machine translation, please write to editor@tadviser.ru. We will make every effort to correct them as soon as possible. |